AUG-US 33/Willipie St Infield TP
AUG County · est $2.6M
Bid dateThursday, March 12—
Awarded toHELMS AND SONS EXCAVATING$2.41M
AUG County · est $2.6M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 3,046 CY | $188.92 | $575k | 24% |
| 442E10100 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 1,253 CY | $232.34 | $291k | 12% |
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 752 CY | $271.06 | $204k | 8% |
| 304E20000 AGGREGATE BASE | 3,093 CY | $46.51 | $144k | 6% |
| 206E10500 CEMENT | 478 TON | $228 | $109k | 5% |
| 203E20000 EMBANKMENT | 2,512 CY | $34 | $85k | 4% |
| 206E15010 CEMENT STABILIZED SUBGRADE, 12 INCHES DEEP | 18,452 SY | $4 | $74k | 3% |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 4,767 FT | $15 | $72k | 3% |
| 609E28000 CURB, TYPE 7 | 2,209 FT | $27 | $60k | 2% |
| 625E15700 LIGHT TOWER FOUNDATION, MISC.: 36" X 10' DEEP | 7 EACH | $8,420 | $59k | 2% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 74 more items below.
| Item | Quantity | R1Helms And Sons Excavating | R2Eagle Bridge CO | R3R D Jones Excavating INC | R4Complete General Construction Company | R5Great Lakes Construction CO | % of bid |
|---|---|---|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 3,046 CY | $189 | $170 | $173 | $170 | — | 30% |
| 442E10100 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 1,253 CY | $232 | $223 | $194 | $223 | — | 15% |
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 752 CY | $271 | $252 | $223 | $252 | — | 11% |
| 304E20000 AGGREGATE BASE | 3,093 CY | $46.51 | $48.45 | $41.67 | $53.29 | $53.29 | 7% |
| 206E10500 CEMENT | 478 TON | $228 | $220 | $225 | $219 | $200 | 6% |
| 203E20000 EMBANKMENT | 2,512 CY | $34.00 | $18.00 | $4.00 | $14.00 | $14.00 | 4% |
| 206E15010 CEMENT STABILIZED SUBGRADE, 12 INCHES DEEP | 18,452 SY | $4.00 | $5.50 | $3.65 | $7.00 | $3.95 | 4% |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 4,767 FT | $15.00 | $13.00 | $25.50 | $14.00 | $14.00 | 4% |
| 609E28000 CURB, TYPE 7 | 2,209 FT | $27.00 | $20.00 | $36.00 | $20.00 | $42.00 | 3% |
| 625E15700 LIGHT TOWER FOUNDATION, MISC.: 36" X 10' DEEP | 7 EACH | $8,420 | $8,000 | $18,500 | $8,000 | $7,610 | 3% |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 1,098 SF | $32.00 | $28.50 | $30.00 | $28.50 | $28.50 | 2% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $97,209.00 2 $111,175.00 3 $108,464.65 4 $150,751.04 5 $122,627.00 | 30,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 624E10000 MOBILIZATION Section 10 - INCIDENTALS - Totals Awd $82,000.00 2 $202,500.00 3 $86,500.00 4 $160,750.00 5 $255,000.00 | 1 LS | $30,000 | $115,000 | $24,000 | $120,000 | $175,000 | 2% |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 1,991 FT | $13.00 | $13.00 | $26.00 | $14.00 | $16.00 | 1% |
| 625E24320 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 2400 VOLT C | 1,657 FT | $15.00 | $16.00 | $25.00 | $16.00 | $14.01 | 1% |
| 611E98151 CATCH BASIN, NO. 3, AS PER PLAN | 6 EACH | $4,025 | $5,000 | $4,400 | $6,000 | $6,200 | 1% |
| 625E13500 LIGHT TOWER, MISC.: INSTALLATION ONLY, BB45 | 7 EACH | $3,400 | $2,200 | $7,500 | $2,200 | $3,070 | 1% |
| 609E70000 4" CONCRETE MEDIAN Section 4 - PAVEMENT - Totals Awd $240,639.00 2 $236,896.00 3 $270,375.00 4 $251,118.00 5 $299,001.00 | 575 SY | $41.00 | $60.00 | $87.00 | $50.00 | $40.00 | 1% |
| 206E11000 CURING COAT | 18,452 SY | $1.25 | $1.30 | $1.45 | $1.29 | $1.20 | 1% |
| 625E26262 LUMINAIRE, HIGH MAST, SOLID STATE (LED), TYPE V | 14 EACH | $1,616 | $1,000 | $2,600 | $1,000 | $1,460 | 1% |
| Item | Quantity | R1Helms And Sons Excavating | R2Eagle Bridge CO | R3R D Jones Excavating INC | R4Complete General Construction Company | R5Great Lakes Construction CO |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $15,000 | $5,000 | $60,000 | $3,000 | $31,500 |
| 202E23000 PAVEMENT REMOVED | 267 SY | $16.00 | $30.00 | $20.00 | $18.00 | $25.00 |
| 202E30600 CONCRETE MEDIAN REMOVED | 8 SY | $96.00 | $90.00 | $100 | $43.00 | $35.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 143 FT | $24.00 | $30.00 | $45.00 | $35.00 | $25.00 |
| 203E10000 EXCAVATION | 2,884 CY | $6.00 | $18.00 | $7.50 | $42.00 | $15.00 |
| 204E10000 SUBGRADE COMPACTION | 110 SY | $13.00 | $12.00 | $5.50 | $10.00 | $3.00 |
| 204E45000 PROOF ROLLING | 7 HOUR | $122 | $300 | $175 | $350 | $390 |
| 206E30000 MIXTURE DESIGN FOR CHEMICALLY STABILIZED SOILS | 1 LS | $12,500 | $9,500 | $9,450 | $9,355 | $8,500 |
| 607E98000 FENCE, MISC.: WOODEN SLAT FENCE | 56 FT | $175 | $156 | $235 | $265 | $265 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $2,800 | $3,500 | $2,750 | $10,500 | $3,000 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $2,800 | $3,500 | $2,750 | $10,500 | $3,000 |
| 690E50600 SPECIAL - BOLLARD Section 1 - ROADWAY - Totals Awd $369,725.00 2 $379,312.60 3 $340,848.20 4 $481,785.28 5 $348,359.12 | 5 EACH | $1,500 | $975 | $1,000 | $1,145 | $975 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 229 SY | $90.00 | $100 | $88.00 | $150 | $115 |
| 659E00300 TOPSOIL | 987 CY | $14.00 | $10.00 | $14.15 | $55.00 | $30.00 |
| 659E10000 SEEDING AND MULCHING | 8,500 SY | $1.00 | $2.00 | $2.00 | $1.09 | $1.09 |
| 659E14000 REPAIR SEEDING AND MULCHING | 425 SY | $1.00 | $3.00 | $1.50 | $2.00 | $2.00 |
| 659E15000 INTER-SEEDING | 425 SY | $1.00 | $3.00 | $1.50 | $2.00 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 1.2 TON | $950 | $1,500 | $1,276 | $500 | $500 |
| 659E31000 LIME | 1.8 ACRE | $40.00 | $5.00 | $625 | $10.00 | $10.00 |
| 659E35000 WATER | 47 MGAL | $1.00 | $15.00 | $100 | $1.00 | $1.00 |
| 670E00700 DITCH EROSION PROTECTION | 526 SY | $2.00 | $3.50 | $7.90 | $2.00 | $2.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $970 | $3,500 | $3,500 | $3,000 | $3,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $7,150 | $10,000 | $8,560 | $6,500 | $10,000 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $13,000 | $11,000 | $2,500 | $9,934 | $11,000 |
| 602E20000 CONCRETE MASONRY | 1 CY | $2,850 | $2,500 | $500 | $2,500 | $5,000 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 475 FT | $11.00 | $20.00 | $31.00 | $30.00 | $25.00 |
| 611E04200 12" CONDUIT, TYPE A | 142 FT | $74.00 | $100 | $115 | $105 | $110 |
| 611E04400 12" CONDUIT, TYPE B | 130 FT | $62.00 | $90.00 | $40.00 | $110 | $85.00 |
| 611E04901 12" CONDUIT, TYPE D, AS PER PLAN748.01 | 106 FT | $135 | $200 | $125 | $175 | $175 |
| 611E10400 24" CONDUIT, TYPE B | 54 FT | $111 | $200 | $73.00 | $175 | $130 |
| 611E10600 24" CONDUIT, TYPE C | 221 FT | $80.00 | $125 | $46.00 | $150 | $120 |
| 611E98510 CATCH BASIN, NO. 2-3 | 1 EACH | $2,600 | $2,750 | $2,700 | $4,500 | $2,900 |
| 611E98634 CATCH BASIN RECONSTRUCTED TO GRADE | 1 EACH | $520 | $1,000 | $2,500 | $1,250 | $2,200 |
| 611E99900 DRAINAGE STRUCTURE, MISC.: CURB CUT Section 3 - DRAINAGE - Totals Awd $196,215.00 2 $226,129.00 3 $278,137.50 4 $244,942.00 5 $253,329.00 | 14 EACH | $495 | $500 | $650 | $105 | $1,200 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 291 FT | $3.00 | $3.00 | $5.00 | $3.00 | $3.00 |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 89 SY | $108 | $77.00 | $100 | $120 | $155 |
| 609E54000 6" CONCRETE TRAFFIC ISLAND | 8 SY | $385 | $80.00 | $200 | $225 | $465 |
| 625E00470 CONNECTION, UNFUSED BOLTED | 15 EACH | $163 | $145 | $160 | $145 | $148 |
| 625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE | 1,143 FT | $5.00 | $3.25 | $10.00 | $3.25 | $4.62 |
| 625E25408 CONDUIT, 2", 725.051 | 217 FT | $7.00 | $12.00 | $15.00 | $12.00 | $6.68 |
| 625E25906 CONDUIT, JACKED OR DRILLED, 725.051, 2" | 124 FT | $23.00 | $35.00 | $75.00 | $35.00 | $21.26 |
| 625E29000 TRENCH | 1,780 FT | $10.00 | $5.50 | $28.00 | $5.50 | $9.24 |
| 625E30700 PULL BOX, 725.08, 18" | 8 EACH | $1,508 | $1,350 | $1,850 | $1,350 | $1,362 |
| 625E32000 GROUND ROD | 8 EACH | $493 | $335 | $325 | $335 | $446 |
| 625E34001 POWER SERVICE, AS PER PLAN | 1 EACH | $5,263 | $6,500 | $5,800 | $8,000 | $4,755 |
| 625E34450 CONTROL CENTER CABINET, COMPLETE | 1 EACH | $13,400 | $3,750 | $18,500 | $3,750 | $12,104 |
| 625E36010 UNDERGROUND WARNING MARKING TAPE | 1,780 FT | $0.15 | $1.75 | $3.00 | $1.75 | $0.13 |
| 625E76000 ARC FLASH CALCULATIONS AND LABEL, LIGHTING POWER S | 1 EACH | $4,115 | $3,500 | $5,500 | $3,500 | $3,715 |
| 632E69100 POWER CABLE, 1 CONDUCTOR, NO. 4 AWG Section 5 - LIGHTING - Totals Awd $203,248.00 2 $168,525.75 3 $392,964.00 4 $170,025.75 5 $184,801.09 | 729 FT | $5.00 | $5.00 | $6.00 | $5.00 | $4.24 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 448 FT | $18.00 | $16.00 | $17.75 | $16.00 | $16.00 |
| 630E07000 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W8X18 | 324 FT | $67.00 | $60.00 | $65.00 | $60.00 | $60.00 |
| 630E07500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X22 | 207 FT | $78.00 | $70.00 | $75.00 | $70.00 | $70.00 |
| 630E08600 SIGN POST REFLECTOR | 7 EACH | $50.00 | $45.00 | $71.75 | $45.00 | $45.00 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 22 EACH | $860 | $780 | $785 | $780 | $780 |
| 630E80100 SIGN, FLAT SHEET | 188 SF | $23.00 | $20.50 | $25.00 | $20.50 | $20.50 |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION Section 6 - TRAFFIC CONTROL - Totals Awd $126,208.00 2 $113,190.00 3 $132,949.25 4 $113,190.00 5 $113,190.00 | 22 EACH | $980 | $885 | $1,500 | $885 | $885 |
| 614E12420 DETOUR SIGNING Section 7 - MAINTENANCE OF TRAFFIC - Totals Awd $4,315.00 2 $5,000.00 3 $4,000.00 4 $5,000.00 5 $3,895.58 | 1 LS | $4,315 | $5,000 | $4,000 | $5,000 | $3,896 |
| 407E20000 NON-TRACKING TACK COAT | 2,255 GAL | $3.87 | $2.42 | $1.94 | $2.42 | — |
| 644E00104 EDGE LINE, 6" | 0.06 MILE | $18,333 | $16,708 | $18,750 | $21,250 | — |
| 644E00300 CENTER LINE | 0.02 MILE | $6,000 | $5,375 | $6,000 | $6,800 | — |
| 644E00404 CHANNELIZING LINE, 12" | 1,473 FT | $2.00 | $1.70 | $2.00 | $1.75 | — |
| 644E00500 STOP LINE | 75 FT | $6.00 | $5.50 | $6.00 | $8.50 | — |
| 644E01200 PARKING LOT STALL MARKING | 6,200 FT | $1.25 | $1.15 | $1.25 | $1.55 | — |
| 644E01300 LANE ARROW Section 8 - ITEMS OF WORK (OPTION A: ASPHALT) - Totals Awd $1,093,463.00 2 $1,003,059.10 3 $954,617.65 4 $1,006,138.75 | 14 EACH | $140 | $125 | $150 | $125 | — |
| 452E14020 10" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P Awd 3 4 | 18,033 SY | — | — | — | — | $94.88 |
| 646E10010 EDGE LINE, 6" Awd 3 4 | 0.06 MILE | — | — | — | — | $21,458 |
| 646E10200 CENTER LINE Awd 3 4 | 0.02 MILE | — | — | — | — | $6,885 |
| 646E10310 CHANNELIZING LINE, 12" Awd 3 4 | 1,473 FT | — | — | — | — | $2.55 |
| 646E10400 STOP LINE Awd 3 4 | 75 FT | — | — | — | — | $12.50 |
| 646E20200 PARKING LOT STALL MARKING Awd 3 4 | 6,200 FT | — | — | — | — | $1.35 |
| 646E20300 LANE ARROW Awd 3 4 Section 9 - ITEMS OF WORK (OPTION B: CONCRETE) - Totals Awd 3 4 5 $1,728,270.85 | 14 EACH | — | — | — | — | $200 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $20,000 | $50,000 | $12,500 | $18,250 | $25,000 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $15,000 | $7,500 | $25,000 | $5,000 | $30,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $17,000 | $30,000 | $25,000 | $17,500 | $25,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →