WYA-US 30 Rest Areas TP
WYA County · est $3.9M
Bid dateThursday, March 12—
Awarded toEAGLE BRIDGE CO$3.39M
WYA County · est $3.9M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 452E14010 10" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 15,522 SY | $87.5 | $1.36M | 40% |
| 304E20000 AGGREGATE BASE | 4,433 CY | $65 | $288k | 8% |
| 203E10000 EXCAVATION | 19,196 CY | $13 | $250k | 7% |
| 202E23000 PAVEMENT REMOVED | 12,653 SY | $13 | $164k | 5% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $273,500.00 2 $86,100.00 3 $201,400.00 4 $312,800.00 5 $330,500.00 6 $213,199.42 7 $292,000.00 8 $308,480.00 9 $257,500.00 10 $255,200.00 | 1 LS | $157,500 | $158k | 5% |
| 206E10500 CEMENT | 419 TON | $223.5 | $94k | 3% |
| 625E15000 LIGHT TOWER FOUNDATION, 36" X 15' DEEP | 10 EACH | $9,200 | $92k | 3% |
| 206E15010 CEMENT STABILIZED SUBGRADE, 12 INCHES DEEP | 16,203 SY | $5.5 | $89k | 3% |
| 609E28000 CURB, TYPE 7 | 2,651 FT | $23 | $61k | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $50,000 | $50k | 1% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 61 more items below.
| Item | Quantity | R1Eagle Bridge CO | R2Helms And Sons Excavating | R3Trucco Construction CO INC | R4Great Lakes Construction CO | R5Advanced Excavating & Demolition | R6LLC Mosser Construction INC | R7Kokosing Construction Company INC | R8Shelly & Sands INC | R9Complete General Construction Company | R10Rietschlin Construction INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 452E14010 10" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 15,522 SY | $87.50 | $92.00 | $96.40 | $90.00 | $86.00 | $82.00 | $87.00 | $110 | $94.25 | $96.00 | 46% |
| 304E20000 AGGREGATE BASE | 4,433 CY | $65.00 | $56.00 | $63.00 | $60.00 | $67.00 | $140 | $77.00 | $77.00 | $80.00 | $68.00 | 10% |
| 203E10000 EXCAVATION | 19,196 CY | $13.00 | $11.00 | $11.00 | $10.50 | $9.75 | $9.50 | $18.00 | $13.00 | $35.00 | $27.00 | 8% |
| 202E23000 PAVEMENT REMOVED | 12,653 SY | $13.00 | $13.50 | $13.00 | $12.00 | $15.00 | $15.15 | $11.00 | $12.00 | $15.00 | $16.00 | 6% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $273,500.00 2 $86,100.00 3 $201,400.00 4 $312,800.00 5 $330,500.00 6 $213,199.42 7 $292,000.00 8 $308,480.00 9 $257,500.00 10 $255,200.00 | 1 LS | $157,500 | $20,000 | $100,000 | $175,000 | $150,000 | $100,000 | $185,000 | $192,000 | $100,000 | $150,000 | 5% |
| 206E10500 CEMENT | 419 TON | $224 | $245 | $235 | $200 | $200 | $200 | $200 | $215 | $223 | $273 | 3% |
| 625E15000 LIGHT TOWER FOUNDATION, 36" X 15' DEEP | 10 EACH | $9,200 | $7,078 | $9,300 | $6,182 | $6,500 | $6,182 | $7,250 | $9,877 | $9,200 | $7,357 | 3% |
| 206E15010 CEMENT STABILIZED SUBGRADE, 12 INCHES DEEP | 16,203 SY | $5.50 | $5.00 | $3.05 | $4.40 | $4.50 | $4.64 | $5.25 | $4.20 | $6.20 | $5.00 | 3% |
| 609E28000 CURB, TYPE 7 | 2,651 FT | $23.00 | $25.00 | $33.00 | $35.00 | $20.00 | $17.00 | $35.00 | $35.00 | $36.38 | $26.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $50,000 | $20,000 | $20,800 | $27,500 | $70,000 | $18,699 | $15,000 | $22,000 | $30,000 | $50,000 | 2% |
| 625E26262 LUMINAIRE, HIGH MAST, SOLID STATE (LED), HMLED_P3_ | 40 EACH | $1,200 | $1,300 | $1,220 | $1,203 | $1,225 | $1,203 | $1,500 | $1,289 | $1,200 | $1,432 | 2% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $136,392.50 2 $193,084.05 3 $102,730.40 4 $134,519.87 5 $147,366.80 6 $177,453.87 7 $113,515.85 8 $124,843.55 9 $167,075.08 10 $201,126.75 | 44,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 608E10000 4" CONCRETE WALK | 6,186 SF | $7.00 | $6.25 | $12.70 | $8.00 | $6.75 | $7.50 | $9.50 | $10.00 | $9.00 | $7.50 | 1% |
| 611E04401 12" CONDUIT, TYPE B, AS PER PLAN | 472 FT | $90.00 | $128 | $82.00 | $130 | $90.00 | $66.00 | $210 | $112 | $135 | $153 | 1% |
| 203E20000 EMBANKMENT | 3,118 CY | $13.00 | $8.00 | $2.60 | $3.50 | $10.75 | $4.20 | $3.00 | $20.00 | $7.00 | $11.00 | 1% |
| 625E10503 LIGHT POLE (INSTALLATION ONLY), AS PER PLAN (LIGHT | 10 EACH | $3,000 | $2,290 | $3,050 | $2,000 | $2,000 | $2,000 | $7,250 | $3,221 | $3,000 | $2,380 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $30,000 | $18,500 | $25,000 | $56,100 | $50,000 | $72,000 | $40,000 | $45,800 | $85,000 | $25,000 | 1% |
| 625E23300 NO. 2 AWG 2400 VOLT DISTRIBUTION CABLE | 5,850 FT | $5.00 | $8.50 | $5.10 | $7.74 | $8.00 | $7.74 | $5.75 | $5.40 | $5.00 | $9.25 | 1% |
| 646E20200 PARKING LOT STALL MARKING | 15,894 FT | $1.75 | $2.00 | $1.90 | $1.75 | $3.50 | $2.75 | $1.75 | $2.00 | $1.75 | $2.25 | 1% |
| 659E00300 TOPSOIL | 1,800 CY | $15.00 | $45.00 | $5.00 | $24.00 | $35.00 | $51.00 | $14.00 | $20.00 | $40.00 | $48.00 | 1% |
| Item | Quantity | R1Eagle Bridge CO | R2Helms And Sons Excavating | R3Trucco Construction CO INC | R4Great Lakes Construction CO | R5Advanced Excavating & Demolition | R6LLC Mosser Construction INC | R7Kokosing Construction Company INC | R8Shelly & Sands INC | R9Complete General Construction Company | R10Rietschlin Construction INC |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $15,000 | $35,750 | $6,700 | $8,500 | $65,000 | $3,600 | $45,000 | $45,000 | $30,000 | $30,000 |
| 202E30000 WALK REMOVED | 2,459 SF | $1.25 | $1.00 | $1.90 | $1.50 | $4.25 | $1.50 | $3.00 | $0.90 | $4.50 | $3.00 |
| 202E32000 CURB REMOVED | 4,628 FT | $3.00 | $2.00 | $3.20 | $2.00 | $7.00 | $2.50 | $5.00 | $3.00 | $9.00 | $4.00 |
| 202E34900 PIPE REMOVED | 938 FT | $12.00 | $26.00 | $31.00 | $37.00 | $12.00 | $15.00 | $20.00 | $28.00 | $20.00 | $54.00 |
| 202E58000 MANHOLE REMOVED | 1 EACH | $325 | $825 | $830 | $1,400 | $950 | $800 | $1,200 | $1,000 | $700 | $3,900 |
| 202E58200 INLET REMOVED | 10 EACH | $250 | $412 | $1,570 | $900 | $725 | $450 | $950 | $718 | $600 | $820 |
| 204E45000 PROOF ROLLING | 8 HOUR | $150 | $115 | $334 | $200 | $360 | $240 | $220 | $500 | $250 | $500 |
| 206E11000 CURING COAT | 16,203 SY | $1.30 | $1.10 | $1.00 | $1.20 | $1.25 | $1.20 | $1.20 | $1.30 | $1.29 | $1.25 |
| 607E98000 FENCE, MISC.:DUMPSTER SCREEN WALL | 104 FT | $225 | $215 | $225 | $193 | $195 | $195 | $222 | $225 | $200 | $268 |
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 500 SF | $7.00 | $6.25 | $14.40 | $16.00 | $14.00 | $7.50 | $18.50 | $14.50 | $12.00 | $10.50 |
| 690E50600 SPECIAL - BOLLARD Section 1 - ROADWAY - Totals Awd $782,738.65 2 $767,074.30 3 $738,213.35 4 $695,542.30 5 $802,560.00 6 $687,189.57 7 $893,017.55 8 $846,996.60 9 $1,302,535.28 10 $1,181,071.75 | 12 EACH | $575 | $1,400 | $580 | $920 | $1,325 | $920 | $1,063 | $1,000 | $950 | $685 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 2 SY | $200 | $250 | $500 | $130 | $275 | $161 | $140 | $253 | $170 | $261 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 18 CY | $100 | $200 | $134 | $170 | $170 | $168 | $250 | $208 | $160 | $250 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $450 | $1,350 | $620 | $70.00 | $70.00 | $397 | $70.00 | $150 | $100 | $180 |
| 659E10000 SEEDING AND MULCHING | 16,215 SY | $1.65 | $2.00 | $0.90 | $0.92 | $0.95 | $0.92 | $0.92 | $1.00 | $1.34 | $1.75 |
| 659E14000 REPAIR SEEDING AND MULCHING | 811 SY | $3.00 | $1.20 | $1.10 | $0.92 | $0.50 | $0.92 | $1.00 | $1.50 | $1.34 | $1.00 |
| 659E15000 INTER-SEEDING | 811 SY | $3.00 | $1.20 | $1.10 | $0.70 | $0.50 | $0.70 | $0.50 | $0.50 | $1.34 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 2.26 TON | $1,250 | $940 | $1,020 | $850 | $820 | $850 | $820 | $820 | $500 | $1,400 |
| 659E31000 LIME | 3.35 ACRE | $5.00 | $55.00 | $730 | $35.00 | $1.00 | $35.00 | $1.00 | $1.00 | $10.00 | $150 |
| 659E35000 WATER | 90 MGAL | $12.00 | $1.10 | $15.00 | $1.00 | $0.50 | $1.00 | $0.50 | $0.50 | $1.00 | $12.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $3,250 | $3,000 | $2,800 | $4,000 | $1,500 | $2,800 | $2,800 | $3,000 | $5,000 | $2,100 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $12,500 | $9,500 | $6,400 | $10,500 | $6,500 | $6,420 | $8,560 | $6,890 | $7,500 | $14,500 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $11,000 | $12,000 | $13,400 | $11,000 | $10,500 | $9,934 | $10,000 | $10,665 | $10,000 | $14,000 |
| 611E00400 4" CONDUIT, TYPE E | 220 FT | $25.00 | $62.00 | $25.00 | $15.00 | $30.00 | $18.00 | $18.00 | $27.00 | $25.00 | $22.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 32 FT | $23.00 | $45.00 | $32.00 | $23.00 | $52.00 | $50.00 | $30.00 | $31.00 | $25.00 | $37.00 |
| 611E05901 15" CONDUIT, TYPE B, AS PER PLAN | 10 FT | $200 | $250 | $274 | $365 | $75.00 | $185 | $425 | $330 | $175 | $620 |
| 611E07401 18" CONDUIT, TYPE B, AS PER PLAN | 10 FT | $220 | $240 | $262 | $525 | $200 | $200 | $450 | $353 | $190 | $640 |
| 611E07900 18" CONDUIT, TYPE D | 178 FT | $65.00 | $140 | $72.00 | $110 | $85.00 | $82.00 | $155 | $94.00 | $140 | $130 |
| 611E98150 CATCH BASIN, NO. 3 | 5 EACH | $4,500 | $4,400 | $5,900 | $6,000 | $4,000 | $5,500 | $5,000 | $5,300 | $4,000 | $5,500 |
| 611E98180 CATCH BASIN, NO. 3A | 1 EACH | $3,900 | $3,800 | $4,200 | $5,500 | $3,500 | $4,500 | $4,250 | $4,800 | $4,000 | $5,700 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $2,250 | $2,400 | $3,150 | $3,600 | $3,000 | $3,000 | $2,750 | $2,800 | $2,150 | $2,525 |
| 611E98860 INLET, NO. 2-A-10 | 2 EACH | $7,000 | $8,500 | $9,100 | $6,900 | $6,000 | $10,500 | $8,250 | $9,000 | $6,500 | $10,000 |
| 611E99574 MANHOLE, NO. 3 | 2 EACH | $4,000 | $4,700 | $4,240 | $6,000 | $3,650 | $6,950 | $5,200 | $6,000 | $5,000 | $5,700 |
| 611E99661 MANHOLE RECONSTRUCTED TO GRADE, AS PER PLAN | 1 EACH | $1,725 | $1,500 | $2,550 | $3,000 | $1,500 | $3,680 | $2,800 | $8,000 | $3,250 | $3,450 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET Section 3 - DRAINAGE - Totals Awd $117,186.00 2 $162,066.00 3 $130,484.00 4 $162,231.00 5 $117,424.00 6 $129,188.00 7 $202,455.00 8 $156,058.00 9 $151,290.00 10 $185,155.00 | 1 EACH | $325 | $650 | $1,000 | $455 | $1,500 | $450 | $375 | $600 | $300 | $600 |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 156 SY | $64.50 | $82.00 | $130 | $215 | $95.00 | $74.00 | $90.00 | $170 | $98.00 | $87.00 |
| 609E26000 CURB, TYPE 6 | 368 FT | $24.00 | $26.00 | $34.00 | $50.00 | $19.25 | $16.50 | $43.00 | $59.50 | $48.50 | $35.25 |
| 609E98000 CURB, MISC.:CURB, TYPE 7 TURNOUT Section 4 - PAVEMENT - Totals Awd $1,731,737.00 2 $1,768,907.00 3 $1,913,974.80 4 $1,827,685.00 5 $1,717,827.00 6 $1,961,657.00 7 $1,830,404.00 8 $2,212,062.00 9 $1,959,532.58 10 $1,891,226.00 | 10 FT | $555 | $400 | $1,810 | $2,000 | $1,100 | $555 | $1,600 | $2,210 | $1,236 | $420 |
| 625E00450 CONNECTION, FUSED PULL APART | 20 EACH | $100 | $200 | $102 | $176 | $176 | $176 | $225 | $107 | $100 | $209 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 33 EACH | $150 | $194 | $152 | $170 | $170 | $170 | $180 | $161 | $150 | $202 |
| 625E23302 NO. 6 AWG 2400 VOLT DISTRIBUTION CABLE | 4,935 FT | $2.75 | $5.50 | $2.80 | $5.04 | $5.25 | $5.04 | $3.00 | $3.00 | $2.75 | $6.00 |
| 625E25504 CONDUIT, 3", 725.051 | 3,490 FT | $7.25 | $10.20 | $7.40 | $9.31 | $9.50 | $9.31 | $12.50 | $7.80 | $7.25 | $11.25 |
| 625E29002 TRENCH, 24" DEEP | 3,490 FT | $5.50 | $14.00 | $5.60 | $12.64 | $12.75 | $12.64 | $12.00 | $6.00 | $5.50 | $15.25 |
| 625E30706 PULL BOX, 725.08, 24" | 11 EACH | $1,500 | $1,600 | $1,520 | $1,420 | $1,425 | $1,420 | $2,500 | $1,610 | $1,500 | $1,690 |
| 625E31510 PULL BOX REMOVED | 3 EACH | $500 | $735 | $510 | $640 | $650 | $640 | $400 | $537 | $500 | $762 |
| 625E32000 GROUND ROD | 20 EACH | $300 | $355 | $305 | $310 | $310 | $310 | $350 | $322 | $300 | $370 |
| 625E36010 UNDERGROUND WARNING MARKING TAPE | 3,490 FT | $1.75 | $2.50 | $1.80 | $2.13 | $2.25 | $2.13 | $0.30 | $2.00 | $1.75 | $2.75 |
| 625E40000 SPECIAL - MAINTAIN EXISTING LIGHTING | 1 LS | $1,600 | $45,000 | $1,630 | $39,960 | $40,000 | $39,960 | $6,000 | $1,718 | $1,600 | $47,600 |
| 625E75350 LIGHT TOWER REMOVED | 2 EACH | $2,000 | $1,350 | $2,030 | $1,160 | $1,175 | $1,160 | $3,500 | $2,147 | $2,000 | $1,381 |
| 625E75506 LUMINAIRE REMOVED | 2 EACH | $250 | $180 | $254 | $160 | $160 | $160 | $150 | $268 | $250 | $191 |
| 625E75540 LIGHT TOWER FOUNDATION REMOVED | 2 EACH | $600 | $2,150 | $610 | $1,860 | $1,900 | $1,860 | $1,800 | $644 | $600 | $2,215 |
| 625E98000 LIGHTING, MISC.:TEST EXISTING CIRCUIT Section 5 - LIGHTING - Totals Awd $305,676.25 2 $411,197.50 3 $310,489.00 4 $368,294.10 5 $376,638.75 6 $368,294.10 7 $408,634.50 8 $329,421.00 9 $305,676.25 10 $440,701.00 | 2 EACH | $2,000 | $2,900 | $2,030 | $2,500 | $2,500 | $2,500 | $2,800 | $2,147 | $2,000 | $2,975 |
| 630E07600 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X12 | 50 FT | $50.00 | $90.00 | $50.00 | $79.00 | $80.00 | $79.00 | $79.00 | $53.00 | $80.95 | $59.50 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 2 EACH | $650 | $960 | $650 | $840 | $840 | $850 | $840 | $700 | $861 | $774 |
| 630E80100 SIGN, FLAT SHEET | 98 SF | $30.00 | $23.00 | $30.00 | $20.00 | $20.00 | $22.50 | $20.00 | $32.00 | $20.49 | $36.00 |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 90 SF | $30.00 | $38.00 | $30.00 | $32.50 | $32.50 | $36.50 | $32.50 | $32.00 | $33.30 | $36.00 |
| 630E82000 SIGN BACKING ASSEMBLY | 12 EACH | $175 | $190 | $175 | $165 | $165 | $165 | $165 | $190 | $169 | $209 |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 2 EACH | $2,500 | $1,700 | $2,500 | $1,475 | $1,500 | $1,480 | $1,475 | $2,700 | $1,511 | $2,975 |
| 646E20320 WRONG WAY ARROW Section 6 - TRAFFIC CONTROL - Totals Awd $46,304.50 2 $51,812.00 3 $48,178.60 4 $45,209.50 5 $73,274.00 6 $61,738.50 7 $45,209.50 8 $51,634.00 9 $45,590.48 10 $57,831.50 | 6 EACH | $325 | $375 | $240 | $325 | $350 | $325 | $325 | $350 | $325 | $387 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $15,000 | $15,000 | $23,800 | $32,000 | $50,000 | $7,500 | $25,000 | $20,000 | $27,500 | $20,000 |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $3,500 | $2,100 | $5,300 | $3,700 | $1,750 | $2,500 | $4,500 | $4,780 | $2,500 | $1,700 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →