POR-US 224-00.00
POR County · est $15M
Bid dateThursday, April 23—
Awarded toSHELLY & SANDS INC$11.0M
POR County · est $15M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (18776 CY | $163 | $3.06M | 28% |
| 441E10100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 10,400 CY | $225 | $2.34M | 21% |
| 255E11000 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 15,000 SY | $121 | $1.81M | 17% |
| 255E12000 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 3,000 SY | $170 | $510k | 5% |
| 624E10000 MOBILIZATION Section 13 - INCIDENTALS - Totals Awd $703,708.23 2 $1,708,250.00 3 $589,664.14 4 $1,327,000.00 5 $1,370,778.89 | 1 LS | $425,000 | $425k | 4% |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 82,350 FT | $2.65 | $218k | 2% |
| 202E23500 WEARING COURSE REMOVED (T = 4-5") | 193,120 SY | $1 | $193k | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $186,088 | $186k | 2% |
| 516E11211 STRUCTURAL EXPANSION JOINT INCLUDING ELASTOMERIC S | 86 FT | $1,800 | $155k | 1% |
| 617E10100 COMPACTED AGGREGATE | 1,556 CY | $75 | $117k | 1% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 93 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Shelly Company | R3Ronyak Paving INC | R4Karvo Companies INC | R5Kokosing Construction Company INC | % of bid |
|---|---|---|---|---|---|---|---|
| 441E10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (18776 CY | $163 | $135 | $175 | $160 | $218 | 31% |
| 441E10100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 10,400 CY | $225 | $190 | $225 | $215 | $270 | 24% |
| 255E11000 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 15,000 SY | $121 | $160 | $158 | $130 | $155 | 18% |
| 255E12000 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 3,000 SY | $170 | $200 | $195 | $180 | $192 | 5% |
| 624E10000 MOBILIZATION Section 13 - INCIDENTALS - Totals Awd $703,708.23 2 $1,708,250.00 3 $589,664.14 4 $1,327,000.00 5 $1,370,778.89 | 1 LS | $425,000 | $400,000 | $316,564 | $849,000 | $705,175 | 4% |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 82,350 FT | $2.65 | $2.50 | $2.00 | $3.00 | $2.51 | 2% |
| 202E23500 WEARING COURSE REMOVED (T = 4-5") | 193,120 SY | $1.00 | $1.95 | $4.00 | $5.97 | $2.80 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $186,088 | $1,182,250 | $180,000 | $300,000 | $557,704 | 2% |
| 516E11211 STRUCTURAL EXPANSION JOINT INCLUDING ELASTOMERIC S | 86 FT | $1,800 | $1,800 | $1,693 | $1,693 | $1,800 | 2% |
| 617E10100 COMPACTED AGGREGATE | 1,556 CY | $75.00 | $95.00 | $90.00 | $85.00 | $40.00 | 1% |
| 516E11211 STRUCTURAL EXPANSION JOINT INCLUDING ELASTOMERIC S | 62 FT | $1,800 | $1,800 | $1,861 | $1,861 | $1,800 | 1% |
| 255E19000 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 300 SY | $350 | $295 | $405 | $230 | $400 | 1% |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT Section 7 - STRUCTURE REPAIR (POR-224-1.307) - Totals Awd $102,150.00 2 $102,150.00 3 $61,002.00 4 $61,002.00 5 $102,150.00 | 90 FT | $1,135 | $1,135 | $678 | $678 | $1,135 | 1% |
| 507E71200 SPECIAL - PILE ENCASEMENT | 175 FT | $520 | $520 | $425 | $425 | $520 | 1% |
| 646E10010 EDGE LINE, 6" | 27.02 MILE | $3,050 | $3,050 | $3,050 | $3,050 | $3,050 | 1% |
| 900E00100 RAILROAD FLAGGING SERVICES (NORFOLK SOUTHERN RAILR Section 5 - MAINTENANCE OF TRAFFIC - Totals Awd $302,715.01 2 $287,195.50 3 $306,115.01 4 $301,215.01 5 $330,179.01 | 81,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 809E69100 STOP LINE RADAR DETECTION Section 4 - TRAFFIC CONTROL - Totals Awd $316,061.95 2 $319,049.95 3 $317,017.95 4 $317,017.95 5 $314,069.95 | 8 EACH | $10,050 | $10,050 | $10,050 | $10,050 | $10,050 | 1% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T = 1.50") | 76,252 SY | $1.00 | $1.30 | $1.25 | $1.85 | $1.40 | 1% |
| 614E12420 DETOUR SIGNING | 1 LS | $62,500 | $62,500 | $65,000 | $62,500 | $96,000 | 1% |
| 407E20000 NON-TRACKING TACK COAT | 19,336 GAL | $3.05 | $3.00 | $2.50 | $2.50 | $2.50 | 1% |
| Item | Quantity | R1Shelly & Sands INC | R2Shelly Company | R3Ronyak Paving INC | R4Karvo Companies INC | R5Kokosing Construction Company INC |
|---|---|---|---|---|---|---|
| 202E98100 REMOVAL MISC.: BARRIER REFLECTOR | 313 EACH | $5.00 | $5.00 | $5.00 | $5.00 | $12.25 |
| 203E10000 EXCAVATION (FOR PAVEMENT REPAIR) | 230 CY | $80.00 | $40.00 | $65.00 | $25.00 | $65.00 |
| 209E60200 LINEAR GRADING | 827 STA | $50.00 | $70.00 | $12.00 | $30.00 | $80.00 |
| 209E72000 PREPARING SUBGRADE FOR SHOULDER PAVING | 962 STA | $30.00 | $88.00 | $10.00 | $25.00 | $9.00 |
| 623E39500 MONUMENT ASSEMBLY ADJUSTED TO GRADE | 1 EACH | $2,500 | $2,500 | $1,750 | $2,500 | $2,500 |
| 690E91000 SPECIAL - AS-BUILT CONSTRUCTION PLANS Section 1 - ROADWAY - Totals Awd $290,795.00 2 $542,395.00 3 $814,289.00 4 $1,216,601.40 5 $640,338.25 | 1 LS | $5,000 | $10,000 | $4,000 | $5,000 | $3,500 |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $3,000.00 2 $3,000.00 3 $3,000.00 4 $3,000.00 5 $3,000.00 | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 300 SY | $100 | $115 | $85.00 | $75.00 | $105 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T = 1.25") | 9,940 SY | $1.00 | $3.25 | $1.50 | $1.75 | $1.30 |
| 304E20000 AGGREGATE BASE (FOR PAVEMENT REPAIR) | 230 CY | $100 | $60.00 | $70.00 | $25.00 | $70.00 |
| 407E13900 TACK COAT, 702.13 | 15,451 GAL | $3.00 | $4.85 | $4.00 | $2.50 | $3.40 |
| 408E10001 PRIME COAT, AS PER PLAN @ 0.40 GAL/SY | 13,256 GAL | $3.50 | $4.85 | $3.00 | $5.50 | $4.00 |
| 441E70500 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $1,000 | $595 | $555 | $500 | $640 |
| 618E41000 RUMBLE STRIPES, EDGE LINE (ASPHALT CONCRETE) | 26.9 MILE | $695 | $695 | $695 | $540 | $695 |
| 618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) | 12.8 MILE | $695 | $695 | $695 | $540 | $695 |
| 874E20000 LONGITUDINAL JOINT PREPARATION Section 3 - PAVEMENT - Totals Awd $8,515,576.80 2 $8,443,784.80 3 $9,422,437.25 4 $8,615,629.70 5 $10,633,027.45 | 66,635 FT | $0.40 | $1.25 | $1.25 | $1.00 | $1.35 |
| 621E00100 RPM | 1,235 EACH | $35.00 | $35.00 | $39.00 | $39.00 | $35.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 996 EACH | $5.00 | $8.00 | $1.00 | $1.00 | $3.00 |
| 626E00102 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 18 EACH | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 373 EACH | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 192 FT | $14.25 | $14.25 | $14.25 | $14.25 | $14.25 |
| 630E80100 SIGN, FLAT SHEET | 36 SF | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 630E80100 SIGN, FLAT SHEET, 730.20 | 14 SF | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 24 EACH | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 24 EACH | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 |
| 646E10200 CENTER LINE | 13.51 MILE | $2,755 | $2,755 | $2,755 | $2,755 | $2,755 |
| 646E10300 CHANNELIZING LINE, 8" | 6,414 FT | $1.60 | $1.60 | $1.60 | $1.60 | $1.60 |
| 646E10400 STOP LINE | 460 FT | $10.75 | $10.75 | $10.75 | $10.75 | $10.75 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 410 FT | $6.75 | $6.75 | $6.75 | $6.75 | $6.75 |
| 646E20300 LANE ARROW | 82 EACH | $160 | $160 | $160 | $160 | $160 |
| 809E69000 ADVANCE RADAR DETECTION | 2 EACH | $10,350 | $10,350 | $10,350 | $10,350 | $10,350 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 30 CY | $200 | $110 | $80.00 | $50.00 | $100 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 300 HOUR | $95.00 | $100 | $125 | $125 | $120 |
| 614E12460 WORK ZONE MARKING SIGN | 18 EACH | $85.00 | $85.00 | $85.00 | $85.00 | $58.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 30 CY | $500 | $125 | $350 | $300 | $125 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 48 SNMT | $875 | $875 | $875 | $875 | $900 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 22.68 MILE | $995 | $900 | $995 | $995 | $995 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 13.51 MILE | $885 | $900 | $885 | $885 | $885 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 27.02 MILE | $635 | $450 | $635 | $635 | $635 |
| 614E23000 WORK ZONE CHANNELIZING LINE, CLASS I, 8" | 12,164 FT | $0.57 | $0.75 | $0.57 | $0.57 | $0.57 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 7,574 FT | $0.52 | $0.75 | $0.52 | $0.52 | $0.52 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 734 FT | $3.10 | $3.00 | $3.10 | $3.10 | $3.10 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 460 FT | $2.95 | $3.00 | $2.95 | $2.95 | $2.95 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND BRIDGES | 1 LS | $3,000 | $3,000 | $2,064 | $2,064 | $3,000 |
| 202E23500 WEARING COURSE REMOVED (T = 2.50") | 173 SY | $10.00 | $10.00 | $60.00 | $5.00 | $35.00 |
| 407E13900 TACK COAT, 702.13 | 14 GAL | $3.00 | $5.00 | $30.00 | $2.50 | $3.40 |
| 407E20000 NON-TRACKING TACK COAT | 11 GAL | $3.05 | $3.00 | $30.00 | $2.50 | $2.50 |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 6 CY | $450 | $335 | $800 | $325 | $272 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (6 CY | $440 | $940 | $800 | $300 | $218 |
| 511E71100 CONCRETE, MISC.: BACKWALL REPAIR | 2 CY | $3,000 | $3,000 | $9,387 | $9,387 | $3,000 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 99 SY | $45.00 | $45.00 | $42.00 | $42.00 | $45.00 |
| 512E73500 TREATING CONCRETE BRIDGE DECKS WITH GRAVITY FED RE | 509 SY | $15.00 | $15.00 | $9.67 | $9.67 | $15.00 |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 74 SY | $45.00 | $45.00 | $23.66 | $23.66 | $45.00 |
| 512E74500 REMOVAL OF EXISTING PAVEMENT MARKING | 444 FT | $5.00 | $5.00 | $1.94 | $1.94 | $5.00 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 10 EACH | $1,000 | $1,000 | $2,337 | $2,337 | $1,000 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $30,000 | $30,000 | $30,120 | $30,120 | $30,000 |
| 519E10000 PATCHING CONCRETE BRIDGE DECK OVERLAY WITH MICRO-S | 10 SY | $1,200 | $1,200 | $780 | $780 | $1,200 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 135 SF | $185 | $185 | $153 | $153 | $185 |
| 530E00800 SPECIAL - STRUCTURES: SPALL REMOVAL WITH ZINC RICH | 10 SY | $1,500 | $1,500 | $565 | $565 | $1,500 |
| 843E50000 PATCHING CONCRETE STRUCTURES WITH TROWELABLE MORTA | 85 SF | $185 | $185 | $153 | $153 | $185 |
| 844E20000 GALVANIC ANODE PROTECTION Section 6 - STRUCTURE REPAIR (POR-224-1.034) - Totals Awd $258,461.55 2 $260,799.00 3 $274,914.89 4 $258,862.39 5 $260,386.10 | 56 EACH | $96.00 | $96.00 | $103 | $103 | $96.00 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND BRIDGES | 1 LS | $3,000 | $3,000 | $1,290 | $1,290 | $3,000 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 2 SY | $500 | $500 | $42.00 | $42.00 | $500 |
| 512E73500 TREATING CONCRETE BRIDGE DECKS WITH GRAVITY FED RE | 748 SY | $15.00 | $15.00 | $9.67 | $9.67 | $15.00 |
| 512E74500 REMOVAL OF EXISTING PAVEMENT MARKING | 465 FT | $5.00 | $5.00 | $1.94 | $1.94 | $5.00 |
| 519E10000 PATCHING CONCRETE BRIDGE DECK OVERLAY WITH MICRO-S | 5 SY | $1,750 | $1,750 | $780 | $780 | $1,750 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 10 SF | $385 | $385 | $153 | $153 | $385 |
| 605E31101 AGGREGATE DRAINS, AS PER PLAN Section 8 - STRUCTURE REPAIR (POR-224-11.717) - Totals Awd $32,345.00 2 $32,345.00 3 $15,924.58 4 $15,924.58 5 $32,345.00 | 44 FT | $50.00 | $50.00 | $22.53 | $22.53 | $50.00 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND BRIDGES | 1 LS | $3,000 | $3,000 | $2,064 | $2,064 | $3,000 |
| 202E23500 WEARING COURSE REMOVED (T = 2.50") | 239 SY | $10.00 | $5.10 | $60.00 | $5.00 | $35.00 |
| 407E13900 TACK COAT, 702.13 | 20 GAL | $3.00 | $5.00 | $30.00 | $2.50 | $3.40 |
| 407E20000 NON-TRACKING TACK COAT | 15 GAL | $3.05 | $3.00 | $30.00 | $2.50 | $2.50 |
| 441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 9 CY | $450 | $275 | $800 | $325 | $272 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (9 CY | $440 | $660 | $800 | $300 | $218 |
| 511E71100 CONCRETE, MISC.: BACKWALL REPAIR | 3 CY | $3,000 | $3,000 | $9,387 | $9,387 | $3,000 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 151 SY | $45.00 | $45.00 | $42.00 | $42.00 | $45.00 |
| 512E73500 TREATING CONCRETE BRIDGE DECKS WITH GRAVITY FED RE | 831 SY | $15.00 | $15.00 | $9.67 | $9.67 | $15.00 |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 126 SY | $45.00 | $45.00 | $23.66 | $23.66 | $45.00 |
| 512E74500 REMOVAL OF EXISTING PAVEMENT MARKING | 522 FT | $5.00 | $5.00 | $1.94 | $1.94 | $5.00 |
| 516E45305 REFURBISH BEARING DEVICE, AS PER PLAN | 12 EACH | $2,250 | $1,000 | $2,300 | $2,300 | $1,000 |
| 516E47001 JACKING AND TEMPORARY SUPPORT OF SUPERSTRUCTURE, A | 1 LS | $18,500 | $18,500 | $30,120 | $30,120 | $18,500 |
| 519E10000 PATCHING CONCRETE BRIDGE DECK OVERLAY WITH MICRO-S | 10 SY | $1,200 | $1,200 | $780 | $780 | $1,200 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN Section 9 - STRUCTURE REPAIR (POR-224-11.892) - Totals Awd $303,970.75 2 $288,243.90 3 $323,819.36 4 $300,936.98 5 $291,345.50 | 225 SF | $185 | $185 | $153 | $153 | $185 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND BRIDGES Section 10 - STRUCTURE REPAIR (POR-224-13.177) - Totals Awd $3,000.00 2 $3,000.00 3 $1,032.00 4 $1,032.00 5 $3,000.00 | 1 LS | $3,000 | $3,000 | $1,032 | $1,032 | $3,000 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND BRIDGES | 1 LS | $3,000 | $3,000 | $1,032 | $1,032 | $3,000 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 14 SY | $45.00 | $45.00 | $42.00 | $42.00 | $45.00 |
| 519E11101 PATCHING CONCRETE STRUCTURE, AS PER PLAN | 125 SF | $185 | $185 | $153 | $153 | $185 |
| 605E31101 AGGREGATE DRAINS, AS PER PLAN Section 11 - STRUCTURE REPAIR (POR-224-7.130) - Totals Awd $119,955.00 2 $119,955.00 3 $95,993.82 4 $95,993.82 5 $119,955.00 | 44 FT | $50.00 | $50.00 | $22.53 | $22.53 | $50.00 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND BRIDGES Section 12 - STRUCTURE REPAIR (POR-224-8.290) - Totals Awd $3,000.00 2 $3,000.00 3 $1,290.00 4 $1,290.00 5 $3,000.00 | 1 LS | $3,000 | $3,000 | $1,290 | $1,290 | $3,000 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $6,620 | $8,000 | $5,000 | $15,000 | $10,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $30,000 | $50,000 | $59,710 | $100,000 | $56,500 |
| 619E16010 FIELD OFFICE, TYPE B | 12 MNTH | $4,000 | $4,000 | $1,500 | $4,000 | $3,200 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,000 | $20,000 | $10,390 | $15,000 | $3,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →