MOT-Old N. Dayton Trail, Seg 2
MOT County · est $1.0M
Bid dateThursday, April 23—
Awarded toBRUMBAUGH CONSTRUCTION INC$1.08M
MOT County · est $1.0M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 304E20000 AGGREGATE BASE | 2,546 CY | $73 | $186k | 17% |
| 607E98200 FENCE, MISC.: OVERHEAD PROTECTIVE FENCING | 1 LS | $160,000 | $160k | 15% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 587 CY | $255 | $150k | 14% |
| 203E10000 EXCAVATION | 5,491 CY | $23 | $126k | 12% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG Section 4 - PAVEMENT - Totals Awd $420,698.00 2 $395,665.00 3 $463,212.27 4 $484,145.68 5 $496,968.50 | 274 CY | $300 | $82k | 8% |
| 624E10000 MOBILIZATION Section 6 - INCIDENTALS - Totals Awd $105,320.00 2 $38,000.00 3 $109,065.00 4 $67,237.22 5 $132,000.00 | 1 LS | $68,320 | $68k | 6% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 940 CY | $66 | $62k | 6% |
| 203E20000 EMBANKMENT | 1,534 CY | $24 | $37k | 3% |
| 659E00511 SEEDING AND MULCHING, CLASS 2, AS PER PLAN | 10,005 SY | $3 | $30k | 3% |
| 204E13000 EXCAVATION OF SUBGRADE | 940 CY | $23 | $22k | 2% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 16 more items below.
| Item | Quantity | R1Brumbaugh Construction INC | R2Fillmore Construction | R3Performance Site Development | R4Sunesis Construction CO | R5Barrett Paving Materials INC | % of bid |
|---|---|---|---|---|---|---|---|
| 304E20000 AGGREGATE BASE | 2,546 CY | $73.00 | $80.00 | $72.00 | $85.68 | $100 | 18% |
| 607E98200 FENCE, MISC.: OVERHEAD PROTECTIVE FENCING | 1 LS | $160,000 | $148,000 | $183,015 | $148,000 | $148,000 | 15% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 587 CY | $255 | $210 | $316 | $300 | $260 | 14% |
| 203E10000 EXCAVATION | 5,491 CY | $23.00 | $30.00 | $25.25 | $34.03 | $45.00 | 12% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG Section 4 - PAVEMENT - Totals Awd $420,698.00 2 $395,665.00 3 $463,212.27 4 $484,145.68 5 $496,968.50 | 274 CY | $300 | $240 | $326 | $310 | $320 | 8% |
| 624E10000 MOBILIZATION Section 6 - INCIDENTALS - Totals Awd $105,320.00 2 $38,000.00 3 $109,065.00 4 $67,237.22 5 $132,000.00 | 1 LS | $68,320 | $17,000 | $29,995 | $31,886 | $40,000 | 7% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 940 CY | $66.00 | $72.00 | $70.00 | $93.95 | $100 | 6% |
| 203E20000 EMBANKMENT | 1,534 CY | $24.00 | $35.00 | $21.00 | $13.76 | $45.00 | 4% |
| 659E00511 SEEDING AND MULCHING, CLASS 2, AS PER PLAN | 10,005 SY | $3.00 | $2.00 | $1.50 | $15.12 | $1.50 | 3% |
| 204E13000 EXCAVATION OF SUBGRADE | 940 CY | $23.00 | $30.00 | $26.25 | $37.24 | $55.00 | 2% |
| 832E30000 EROSION CONTROL | 20,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $18,500 | $7,500 | $24,750 | $19,600 | $36,000 | 2% |
| 670E00500 SLOPE EROSION PROTECTION | 3,556 SY | $3.50 | $2.25 | $4.21 | $2.25 | $3.50 | 1% |
| 204E10000 SUBGRADE COMPACTION | 11,366 SY | $1.00 | $3.00 | $1.00 | $1.56 | $2.50 | 1% |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA Section 2 - EROSION CONTROL - Totals Awd $82,461.00 2 $70,211.00 3 $78,278.26 4 $195,162.61 5 $74,353.50 | 1 LS | $11,000 | $10,000 | $14,150 | $8,835 | $10,000 | 1% |
| 611E07400 18" CONDUIT, TYPE B, 706.02 | 37 FT | $250 | $180 | $177 | $252 | $155 | 1% |
| 608E13020 7" CONCRETE WALK | 922 SF | $10.00 | $50.00 | $13.95 | $11.54 | $12.00 | 1% |
| 611E99660 MANHOLE RECONSTRUCTED TO GRADE Section 3 - DRAINAGE - Totals Awd $18,580.00 2 $19,660.00 3 $22,139.00 4 $11,427.21 5 $18,735.00 | 4 EACH | $2,200 | $2,500 | $2,950 | $320 | $2,500 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,500 | $7,500 | $19,995 | $7,565 | $22,000 | 1% |
| 204E50000 GEOTEXTILE FABRIC | 2,820 SY | $2.50 | $2.00 | $5.00 | $1.11 | $3.50 | 1% |
| Item | Quantity | R1Brumbaugh Construction INC | R2Fillmore Construction | R3Performance Site Development | R4Sunesis Construction CO | R5Barrett Paving Materials INC |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,000 | $7,500 | $33,955 | $2,691 | $28,000 |
| 202E23000 PAVEMENT REMOVED | 13 SY | $40.00 | $50.00 | $125 | $51.30 | $65.00 |
| 204E45001 PROOF ROLLING, AS PER PLAN | 5 HOUR | $325 | $150 | $195 | $227 | $275 |
| 607E23000 FENCE, TYPE CLT | 61 FT | $70.00 | $65.00 | $47.25 | $65.00 | $65.00 |
| 607E98100 FENCE, MISC.: TUBULAR BARRIER SWING GATE | 2 EACH | $3,500 | $3,250 | $4,675 | $3,250 | $3,250 |
| 608E53020 DETECTABLE WARNING Section 1 - ROADWAY - Totals Awd $451,940.00 2 $570,303.00 3 $532,531.16 4 $527,145.28 5 $702,659.00 | 28 SF | $40.00 | $100 | $38.00 | $50.00 | $100 |
| 601E10000 RIPRAP | 10 SY | $50.00 | $120 | $245 | $185 | $390 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,500 | $3,500 | $3,950 | $2,500 | $5,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $6,000 | $7,500 | $7,750 | $2,700 | $8,000 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 2 EACH | $265 | $1,500 | $1,895 | $420 | $1,500 |
| 407E20000 NON-TRACKING TACK COAT | 591 GAL | $5.00 | $5.00 | $8.83 | $8.40 | $3.50 |
| 620E60000 DELINEATOR, POST SURFACE MOUNTED | 1 EACH | $215 | $200 | $446 | $16.00 | $300 |
| 630E97700 SIGNING, MISC.: CSXT NO TRESPASSING SIGN | 4 EACH | $550 | $500 | $704 | $16.00 | $500 |
| 644E00300 CENTER LINE Section 5 - TRAFFIC CONTROL - Totals Awd $4,095.00 2 $3,745.00 3 $4,882.51 4 $1,625.00 5 $3,900.00 | 0.02 MILE | $84,000 | $77,250 | $81,113 | $77,250 | $80,000 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $6,000 | $2,500 | $6,550 | $4,000 | $20,000 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $5,000 | $3,500 | $27,775 | $4,186 | $14,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →