HAN-McComb Ped Improvements
HAN County · est $0.2M
Bid dateThursday, April 23—
Awarded toADVANCED EXCAVATING & DEMOLITION$206,097
HAN County · est $0.2M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 630E97700 SIGNING, MISC.:SOLAR POWERED RECTANGULAR RAPID FLA | 6 EACH | $8,750 | $53k | 25% |
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 1,915 SF | $19 | $36k | 18% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 181 FT | $78 | $14k | 7% |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 195 FT | $65 | $13k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $10k | 5% |
| 608E52001 CURB RAMP, AS PER PLAN | 391 SF | $25 | $10k | 5% |
| 202E30000 WALK REMOVED | 992 SF | $7 | $7k | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $6,500 | $7k | 3% |
| 253E01000 PAVEMENT REPAIR Section 3 - PAVEMENT - Totals Awd $5,100.00 2 $3,300.00 | 6 SY | $850 | $5k | 2% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $9,127.00 2 $12,960.55 | 5,000 EACH | $1 | $5k | 2% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 15 more items below.
| Item | Quantity | R1Advanced Excavating & Demolition | R2LLC Fenson Contracting LLC | % of bid |
|---|---|---|---|---|
| 630E97700 SIGNING, MISC.:SOLAR POWERED RECTANGULAR RAPID FLA | 6 EACH | $8,750 | $10,150 | 27% |
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 1,915 SF | $19.00 | $16.00 | 19% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 181 FT | $78.00 | $75.00 | 7% |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 195 FT | $65.00 | $65.00 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $14,000 | 5% |
| 608E52001 CURB RAMP, AS PER PLAN | 391 SF | $25.00 | $28.00 | 5% |
| 202E30000 WALK REMOVED | 992 SF | $7.00 | $13.25 | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $6,500 | $7,250 | 3% |
| 253E01000 PAVEMENT REPAIR Section 3 - PAVEMENT - Totals Awd $5,100.00 2 $3,300.00 | 6 SY | $850 | $550 | 3% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $9,127.00 2 $12,960.55 | 5,000 EACH | $1.00 | $1.00 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,000 | $2,500 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $5,000 | $10,000 | 3% |
| 630E80100 SIGN, FLAT SHEET | 197 SF | $22.00 | $25.50 | 2% |
| 202E32500 CURB AND GUTTER REMOVED | 123 FT | $30.00 | $15.00 | 2% |
| 512E74500 REMOVAL OF EXISTING PAVEMENT MARKING | 181 FT | $20.00 | $25.00 | 2% |
| 644E00630 CROSSWALK LINE, 24" Section 5 - TRAFFIC CONTROL - Totals Awd $62,668.00 2 $72,671.30 | 416 FT | $8.00 | $9.20 | 2% |
| 202E23000 PAVEMENT REMOVED | 83 SY | $30.00 | $80.00 | 1% |
| 659E00300 TOPSOIL | 30 CY | $75.00 | $150 | 1% |
| 608E53020 DETECTABLE WARNING | 40 SF | $50.00 | $28.00 | 1% |
| 900E17000 SPECIAL - PRECONSTRUCTION VIDEO Section 7 - INCIDENTALS - Totals Awd $28,510.00 2 $34,800.00 | 1 LS | $2,000 | $950 | 1% |
| Item | Quantity | R1Advanced Excavating & Demolition | R2LLC Fenson Contracting LLC |
|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,500 | $3,800 |
| 203E10000 EXCAVATION | 19 CY | $70.00 | $65.00 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $1,500 | $1,500 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND Section 1 - ROADWAY - Totals Awd $97,527.00 2 $103,147.00 | 1 LS | $1,500 | $1,500 |
| 659E10000 SEEDING AND MULCHING | 265 SY | $7.00 | $12.75 |
| 659E14000 REPAIR SEEDING AND MULCHING | 14 SY | $1.50 | $5.70 |
| 659E35000 WATER | 2 MGAL | $0.50 | $1.00 |
| 638E10801 VALVE BOX ADJUSTED TO GRADE, AS PER PLAN Section 4 - WATER WORK - Totals Awd $1,500.00 2 $750.00 | 2 EACH | $750 | $375 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 78 FT | $14.00 | $16.50 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $75.00 | $90.00 |
| 642E00701 TRANSVERSE/DIAGONAL LINE, TYPE 1, AS PER PLAN (4" | 480 FT | $2.00 | $2.30 |
| 644E00500 STOP LINE | 38 FT | $8.00 | $9.20 |
| 607E30000 FENCE, SNOW | 115 FT | $11.00 | $8.00 |
| 614E12461 WORK ZONE MARKING SIGN, AS PER PLAN Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $1,665.00 2 $1,380.00 | 4 EACH | $100 | $115 |
| 616E10000 WATER | 2 MGAL | $5.00 | $50.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →