PER-TR 358-00.00 (THORN TWP)
PER County · est $0.5M
Bid dateThursday, April 9—
Awarded toSHELLY COMPANY$421,582.59
PER County · est $0.5M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 203E20000 EMBANKMENT | 2,319 CY | $30.25 | $70k | 17% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 212 CY | $262.5 | $56k | 13% |
| 659E00300 TOPSOIL | 898 CY | $37.75 | $34k | 8% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 Section 4 - PAVEMENT - Totals Awd $122,990.90 2 $129,586.84 3 $158,264.00 | 448 (103 CY | $298.75 | $31k | 7% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $88,324.94 2 $105,839.30 3 $120,433.75 | 27,495 EACH | $1 | $27k | 7% |
| 304E20000 AGGREGATE BASE | 353 CY | $71.75 | $25k | 6% |
| 203E35120 GRANULAR MATERIAL, TYPE C | 250 CY | $72 | $18k | 4% |
| 611E20700 48" CONDUIT, TYPE A ,CONCRETE | 31 FT | $520 | $16k | 4% |
| 203E10000 EXCAVATION | 255 CY | $42 | $11k | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $10,000 | $10k | 2% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 30 more items below.
| Item | Quantity | R1Shelly Company | R2Law General Contracting INC | R3Layton Services | % of bid |
|---|---|---|---|---|---|
| 203E20000 EMBANKMENT | 2,319 CY | $30.25 | $36.68 | $53.00 | 19% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 212 CY | $263 | $267 | $292 | 15% |
| 659E00300 TOPSOIL | 898 CY | $37.75 | $43.88 | $65.00 | 9% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 Section 4 - PAVEMENT - Totals Awd $122,990.90 2 $129,586.84 3 $158,264.00 | 448 (103 CY | $299 | $319 | $329 | 8% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $88,324.94 2 $105,839.30 3 $120,433.75 | 27,495 EACH | $1.00 | $1.00 | $1.00 | 7% |
| 304E20000 AGGREGATE BASE | 353 CY | $71.75 | $78.00 | $130 | 7% |
| 203E35120 GRANULAR MATERIAL, TYPE C | 250 CY | $72.00 | $66.63 | $90.00 | 5% |
| 611E20700 48" CONDUIT, TYPE A ,CONCRETE | 31 FT | $520 | $431 | $700 | 4% |
| 203E10000 EXCAVATION | 255 CY | $42.00 | $43.53 | $35.00 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $10,000 | $7,380 | $10,000 | 3% |
| 607E98000 FENCE, MISC.:WOOD BIKE RAILING | 80 FT | $125 | $138 | $90.00 | 3% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $27,500.00 2 $35,200.00 3 $30,500.00 | 1 LS | $10,000 | $10,000 | $10,000 | 3% |
| 204E13000 EXCAVATION OF SUBGRADE | 250 CY | $39.00 | $38.70 | $30.00 | 3% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE 1.50" | 2,962 SY | $3.25 | $3.32 | $5.00 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $8,000 | $5,000 | $10,000 | 2% |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $7,135 | $11,000 | $10,000 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $6,500 | $13,200 | $9,500 | 2% |
| 659E10000 SEEDING AND MULCHING | 7,935 SY | $0.73 | $0.80 | $0.75 | 2% |
| 611E04900 12" CONDUIT, TYPE D ,CONCRETE | 57 FT | $88.00 | $93.54 | $125 | 1% |
| 204E10000 SUBGRADE COMPACTION | 2,115 SY | $2.00 | $2.46 | $2.75 | 1% |
| Item | Quantity | R1Shelly Company | R2Law General Contracting INC | R3Layton Services |
|---|---|---|---|---|
| 202E11001 STRUCTURE REMOVED, AS PER PLAN | 1 LS | $3,000 | $525 | $3,420 |
| 204E45000 PROOF ROLLING | 2 HOUR | $270 | $260 | $300 |
| 204E50000 GEOTEXTILE FABRIC | 500 SY | $3.75 | $4.63 | $2.25 |
| 608E53020 DETECTABLE WARNING Section 1 - ROADWAY - Totals Awd $140,234.75 2 $152,311.43 3 $195,713.25 | 88 SF | $22.50 | $32.67 | $65.00 |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 15 CY | $270 | $271 | $300 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $135 | $149 | $100 |
| 659E14000 REPAIR SEEDING AND MULCHING | 319 SY | $0.80 | $0.88 | $0.75 |
| 659E15000 INTER-SEEDING | 319 SY | $0.80 | $0.88 | $0.75 |
| 659E20000 COMMERCIAL FERTILIZER | 0.86 TON | $939 | $1,034 | $1,250 |
| 659E31000 LIME | 1.32 ACRE | $158 | $174 | $150 |
| 659E35000 WATER | 34 MGAL | $1.00 | $1.10 | $1.00 |
| 659E40000 MOWING | 14 MSF | $64.28 | $118 | $100 |
| 670E00500 SLOPE EROSION PROTECTION | 1,711 SY | $1.33 | $1.47 | $2.00 |
| 670E00720 DITCH EROSION PROTECTION MAT, TYPE B | 655 SY | $1.40 | $1.54 | $2.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $3,100 | $3,080 | $2,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $930 | $7,260 | $4,000 |
| 511E46610 CLASS QC1 CONCRETE, HEADWALL | 3 CY | $1,150 | $1,358 | $2,000 |
| 611E05900 15" CONDUIT, TYPE B ,CONCRETE | 10 FT | $192 | $187 | $225 |
| 611E06400 15" CONDUIT, TYPE D ,CONCRETE | 50 FT | $82.50 | $105 | $135 |
| 611E98470 CATCH BASIN, NO. 2-2B Section 3 - DRAINAGE - Totals Awd $33,156.00 2 $32,053.36 3 $47,825.00 | 1 EACH | $2,525 | $2,157 | $4,000 |
| 407E20000 NON-TRACKING TACK COAT | 394 GAL | $4.10 | $7.00 | $4.50 |
| 614E12730 SPECIAL - REBOUNDABLE TUBULAR PYLON | 3 EACH | $400 | $440 | $750 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 183 FT | $20.00 | $22.00 | $18.00 |
| 630E80100 SIGN, FLAT SHEET | 86 SF | $30.00 | $33.00 | $32.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $25.00 | $28.00 | $100 |
| 644E00500 STOP LINE | 11 FT | $20.00 | $13.00 | $20.00 |
| 644E00620 CROSSWALK LINE, 12" | 68 FT | $12.00 | $6.00 | $12.00 |
| 644E00630 CROSSWALK LINE, 24" Section 5 - TRAFFIC CONTROL - Totals Awd $9,374.00 2 $9,533.00 3 $10,380.00 | 53 FT | $16.00 | $14.00 | $16.00 |
| 616E10000 WATER Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $2.00 2 $2.20 3 $2,000.00 | 2 MGAL | $1.00 | $1.10 | $1,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,000 | $7,000 | $1,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →