LUC-/OTT-SR 2-34.05/00.00 Resurf
LUC County · est $3.8M
Bid dateThursday, April 9—
Awarded toKOKOSING CONSTRUCTION COMPANY INC$3.39M
LUC County · est $3.8M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 10,696 CY | $204 | $2.18M | 64% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 257,599 SY | $1.3 | $335k | 10% |
| 253E02000 PAVEMENT REPAIR | 711 CY | $263 | $187k | 6% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $269,153.00 2 $289,000.00 3 $229,610.00 | 1 LS | $169,440 | $169k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $82,863 | $83k | 2% |
| 617E10100 COMPACTED AGGREGATE | 1,380 CY | $40 | $55k | 2% |
| 407E10000 TACK COAT | 21,897 GAL | $2.2 | $48k | 1% |
| 621E00100 RPM | 1,225 EACH | $34.5 | $42k | 1% |
| 209E60500 LINEAR GRADING | 22 MILE | $1,650 | $36k | 1% |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 4,442 FT | $7 | $31k | 1% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 16 more items below.
| Item | Quantity | R1Kokosing Construction Company INC | R2Erie Blacktop INC | R3Gerken Paving INC | % of bid |
|---|---|---|---|---|---|
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 10,696 CY | $204 | $245 | $230 | 65% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 257,599 SY | $1.30 | $0.75 | $2.02 | 10% |
| 253E02000 PAVEMENT REPAIR | 711 CY | $263 | $250 | $240 | 6% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $269,153.00 2 $289,000.00 3 $229,610.00 | 1 LS | $169,440 | $180,000 | $80,000 | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $82,863 | $84,000 | $99,250 | 2% |
| 617E10100 COMPACTED AGGREGATE | 1,380 CY | $40.00 | $65.00 | $76.50 | 2% |
| 407E10000 TACK COAT | 21,897 GAL | $2.20 | $2.50 | $2.50 | 1% |
| 621E00100 RPM | 1,225 EACH | $34.50 | $40.00 | $36.00 | 1% |
| 209E60500 LINEAR GRADING | 22 MILE | $1,650 | $1,850 | $2,200 | 1% |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 4,442 FT | $7.00 | $7.35 | $7.00 | 1% |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 41.98 MILE | $700 | $840 | $800 | 1% |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 26.24 MILE | $900 | $945 | $900 | 1% |
| 874E20000 LONGITUDINAL JOINT PREPARATION Section 4 - PAVEMENT - Totals Awd $2,837,733.44 2 $3,183,237.95 3 $3,444,214.93 | 55,917 FT | $0.42 | $0.60 | $2.25 | 1% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 20.99 MILE | $800 | $840 | $800 | 1% |
| 623E39500 MONUMENT ASSEMBLY ADJUSTED TO GRADE Section 1 - ROADWAY - Totals Awd $52,798.35 2 $57,200.00 3 $64,898.35 | 33 EACH | $500 | $500 | $500 | 0% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $13,550 | $15,000 | $16,000 | 0% |
| 644E00400 CHANNELIZING LINE, 8" | 8,619 FT | $1.50 | $1.55 | $1.50 | 0% |
| 642E00300 CENTER LINE, TYPE 1 | 13.12 MILE | $900 | $945 | $900 | 0% |
| 644E01300 LANE ARROW | 99 EACH | $95.00 | $99.75 | $95.00 | 0% |
| 644E01510 DOTTED LINE, 6" | 5,433 FT | $1.50 | $1.55 | $1.50 | 0% |
| Item | Quantity | R1Kokosing Construction Company INC | R2Erie Blacktop INC | R3Gerken Paving INC |
|---|---|---|---|---|
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $5,000.00 2 $5,000.00 3 $5,000.00 | 5,000 EACH | $1.00 | $1.00 | $1.00 |
| 611E99654 MANHOLE ADJUSTED TO GRADE Section 3 - DRAINAGE - Totals Awd $1,224.95 2 $1,200.00 3 $1,224.95 | 1 EACH | $1,225 | $1,200 | $1,225 |
| 618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) | 13.12 MILE | $535 | $1,050 | $535 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 1,225 EACH | $4.00 | $5.00 | $6.00 |
| 644E00500 STOP LINE | 340 FT | $8.00 | $8.40 | $8.00 |
| 644E00900 ISLAND MARKING | 557 SF | $8.00 | $8.40 | $8.00 |
| 644E01000 RAILROAD SYMBOL MARKING | 2 EACH | $600 | $630 | $600 |
| 644E40000 SPEED MEASUREMENT MARKING Section 5 - TRAFFIC CONTROL - Totals Awd $147,215.50 2 $159,829.35 3 $151,503.00 | 10 EACH | $150 | $158 | $150 |
| 614E12460 WORK ZONE MARKING SIGN | 52 EACH | $95.00 | $99.75 | $120 |
| 614E12500 REPLACEMENT SIGN | 5 EACH | $150 | $158 | $120 |
| 614E12600 REPLACEMENT DRUM | 5 EACH | $35.00 | $36.75 | $55.00 |
| 614E23000 WORK ZONE CHANNELIZING LINE, CLASS I, 8" | 8,619 FT | $0.90 | $1.05 | $1.00 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 8,619 FT | $0.90 | $1.05 | $1.00 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 340 FT | $2.00 | $2.10 | $2.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $75,741.20 2 $85,746.15 3 $82,913.00 | 340 FT | $2.00 | $2.10 | $2.00 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,300 | $10,000 | $34,360 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →