D04-TSG FY2026
D04 County · est $0.6M
Bid dateThursday, April 9—
Awarded toTC RANDEL CONSTRUCTON LLC$591,997.5
D04 County · est $0.6M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 6 EACH | $9,200 | $55k | 9% |
| 633E65511 CABINET, TYPE TS-2, AS PER PLAN | 3 EACH | $17,850 | $54k | 9% |
| 632E72111 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 4, AS PER PL | 4 EACH | $11,300 | $45k | 8% |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 5 EACH | $8,925 | $45k | 8% |
| 625E25902 CONDUIT, JACKED OR DRILLED, 725.04, 4" | 417 FT | $101 | $42k | 7% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 7 EACH | $5,800 | $41k | 7% |
| 632E78349 COMBINATION SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 1 | 1 EACH | $27,500 | $28k | 5% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $79,300.00 2 $47,976.00 3 $85,588.00 4 $85,928.00 5 $74,850.00 | 1 LS | $25,000 | $25k | 4% |
| 632E71245 SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 6 POLE, WITH | 1 EACH | $21,000 | $21k | 4% |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 26 EACH | $805 | $21k | 4% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 31 more items below.
| Item | Quantity | R1Tc Randel Constructon LLC | R2Cornerstone Electric INC | R3Perram Electric INC | R4S E T INC | R5Miller Cable Company | % of bid |
|---|---|---|---|---|---|---|---|
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 6 EACH | $9,200 | $9,000 | $9,840 | $11,000 | $11,250 | 11% |
| 633E65511 CABINET, TYPE TS-2, AS PER PLAN | 3 EACH | $17,850 | $20,000 | $20,660 | $23,000 | $22,250 | 11% |
| 632E72111 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 4, AS PER PL | 4 EACH | $11,300 | $11,750 | $11,030 | $13,500 | $12,600 | 9% |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 5 EACH | $8,925 | $8,750 | $9,555 | $11,000 | $10,850 | 9% |
| 625E25902 CONDUIT, JACKED OR DRILLED, 725.04, 4" | 417 FT | $101 | $75.00 | $117 | $78.00 | $76.00 | 8% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 7 EACH | $5,800 | $9,000 | $7,280 | $8,200 | $7,050 | 8% |
| 632E78349 COMBINATION SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 1 | 1 EACH | $27,500 | $27,500 | $26,875 | $34,000 | $31,000 | 5% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $79,300.00 2 $47,976.00 3 $85,588.00 4 $85,928.00 5 $74,850.00 | 1 LS | $25,000 | $10,000 | $20,000 | $20,000 | $20,000 | 5% |
| 632E71245 SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 6 POLE, WITH | 1 EACH | $21,000 | $20,500 | $20,435 | $26,000 | $23,600 | 4% |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 26 EACH | $805 | $900 | $896 | $1,200 | $1,500 | 4% |
| 632E79131 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN | 1 EACH | $15,300 | $15,250 | $14,720 | $18,000 | $17,300 | 3% |
| 633E75001 UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 WATT, AS | 3 EACH | $5,000 | $6,500 | $5,485 | $7,000 | $7,000 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $15,000 | $5,500 | $33,000 | $40,000 | $26,000 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $14,750 | $6,076 | $11,088 | $6,000 | $4,250 | 3% |
| 632E90100 REMOVAL OF TRAFFIC SIGNAL INSTALLATION | 3 EACH | $4,400 | $2,500 | $5,845 | $2,500 | $3,700 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $12,550 | $12,000 | $3,500 | $9,128 | $15,000 | 3% |
| 619E16010 FIELD OFFICE, TYPE B | 12 MNTH | $1,000 | $1,200 | $1,500 | $900 | $800 | 2% |
| 625E76000 ARC FLASH CALCULATIONS AND LABEL (MEADOWBROOK, WIL | 3 EACH | $3,650 | $500 | $1,500 | $1,200 | $3,650 | 2% |
| 625E30706 PULL BOX, 725.08, 24" | 9 EACH | $985 | $1,500 | $2,283 | $1,200 | $1,500 | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $8,600.00 2 $5,000.00 3 $8,000.00 4 $5,000.00 5 $7,500.00 | 100 HOUR | $86.00 | $50.00 | $80.00 | $50.00 | $75.00 | 2% |
| Item | Quantity | R1Tc Randel Constructon LLC | R2Cornerstone Electric INC | R3Perram Electric INC | R4S E T INC | R5Miller Cable Company |
|---|---|---|---|---|---|---|
| 202E30000 WALK REMOVED | 120 SF | $8.00 | $20.00 | $20.00 | $7.00 | $35.00 |
| 608E52001 CURB RAMP, AS PER PLAN | 105 SF | $32.00 | $60.00 | $60.00 | $50.00 | $85.00 |
| 690E91000 SPECIAL - AS-BUILT CONSTRUCTION PLANS Section 1 - ROADWAY - Totals Awd $5,820.00 2 $9,200.00 3 $11,510.00 4 $8,090.00 5 $15,625.00 | 1 LS | $1,500 | $500 | $2,810 | $2,000 | $2,500 |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $1,000.00 2 $1,000.00 3 $1,000.00 4 $1,000.00 5 $1,000.00 | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E00400 4" CONDUIT, TYPE E | 30 FT | $8.00 | $12.00 | $10.05 | $15.00 | $6.00 |
| 605E31100 AGGREGATE DRAINS Section 3 - DRAINAGE - Totals Awd $483.00 2 $1,710.00 3 $6,214.50 4 $1,530.00 5 $396.00 | 27 FT | $9.00 | $50.00 | $219 | $40.00 | $8.00 |
| 643E00500 STOP LINE | 24 FT | $30.00 | $18.00 | $25.00 | $105 | $95.00 |
| 646E10520 CROSSWALK LINE, 24", HIGH VISIBILITY | 234 FT | $16.00 | $15.00 | $15.00 | $16.00 | $41.00 |
| 646E50100 REMOVAL OF PAVEMENT MARKING Section 4 - TRAFFIC CONTROL - Totals Awd $6,183.00 2 $5,852.00 3 $5,638.00 4 $7,219.00 5 $17,986.00 | 191 FT | $9.00 | $10.00 | $8.00 | $5.00 | $32.00 |
| 625E18400 BRACKET ARM, 20' | 2 EACH | $1,700 | $1,500 | $1,450 | $2,300 | $1,800 |
| 625E25500 CONDUIT, 3", 725.04 | 180 FT | $25.00 | $35.00 | $46.55 | $33.00 | $31.00 |
| 625E26253 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER | 2 EACH | $475 | $500 | $422 | $570 | $500 |
| 625E29000 TRENCH | 16 FT | $30.00 | $50.00 | $12.60 | $30.00 | $15.00 |
| 625E29400 TRENCH IN PAVED AREA | 164 FT | $50.00 | $95.00 | $31.70 | $135 | $39.00 |
| 625E31510 PULL BOX REMOVED | 4 EACH | $200 | $250 | $200 | $120 | $300 |
| 625E32000 GROUND ROD | 10 EACH | $150 | $200 | $326 | $240 | $275 |
| 625E36011 UNDERGROUND WARNING/MARKING TAPE, AS PER PLAN | 180 FT | $2.00 | $2.00 | $0.40 | $2.00 | $3.00 |
| 632E20731 PEDESTRIAN SIGNAL HEAD (LED), TYPE D2, COUNTDOWN, | 10 EACH | $550 | $650 | $492 | $670 | $800 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD | 26 EACH | $25.00 | $25.00 | $20.00 | $50.00 | $50.00 |
| 632E25010 COVERING OF PEDESTRIAN SIGNAL HEAD | 10 EACH | $15.00 | $25.00 | $10.00 | $40.00 | $40.00 |
| 632E26000 PEDESTRIAN PUSHBUTTON | 10 EACH | $375 | $250 | $342 | $250 | $265 |
| 632E40300 SIGNAL CABLE, 3 CONDUCTOR, NO. 14 AWG | 1,567 FT | $2.00 | $3.00 | $2.70 | $2.00 | $2.65 |
| 632E40500 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG | 1,567 FT | $2.50 | $3.50 | $3.30 | $3.00 | $3.15 |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG | 2,444 FT | $3.25 | $4.00 | $3.90 | $3.00 | $3.50 |
| 632E64020 PEDESTAL FOUNDATION | 8 EACH | $900 | $1,000 | $1,605 | $950 | $1,350 |
| 632E69300 POWER CABLE, 3 CONDUCTOR, NO. 4 AWG | 90 FT | $6.00 | $6.00 | $8.45 | $10.00 | $14.00 |
| 632E70001 POWER SERVICE, AS PER PLAN | 3 EACH | $2,200 | $5,000 | $3,205 | $4,000 | $2,700 |
| 632E89900 PEDESTAL, 8', TRANSFORMER BASE | 8 EACH | $865 | $1,200 | $1,618 | $850 | $1,100 |
| 633E67101 CABINET FOUNDATION, AS PER PLAN | 3 EACH | $2,000 | $3,000 | $3,615 | $2,500 | $3,200 |
| 633E67201 CONTROLLER WORK PAD, AS PER PLAN | 3 EACH | $360 | $1,000 | $905 | $600 | $750 |
| 809E69123 ATC CONTROLLER, AS PER PLAN Section 5 - TRAFFIC SIGNALS - Totals Awd $490,611.50 2 $534,216.50 3 $557,944.50 4 $589,233.00 5 $582,800.60 | — | $1,000 | $500 | $550 | $1,000 | $1,100 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →