CLE-SR 32-09.80 Herold Rd
CLE County · est $0.7M
Bid dateThursday, April 9—
Awarded toJOHN R JURGENSEN COMPANY$762,908.99
CLE County · est $0.7M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 413 CY | $365 | $151k | 20% |
| 204E30020 GRANULAR MATERIAL, TYPE C | 631 CY | $104.06 | $66k | 9% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 2,476 FT | $23.17 | $57k | 8% |
| 442E22300 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 88 CY | $595 | $52k | 7% |
| 442E22100 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 75 CY | $685 | $51k | 7% |
| 304E20000 AGGREGATE BASE | 367 CY | $115.97 | $43k | 6% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $70,979.55 2 $114,285.83 3 $79,615.80 | 1 LS | $37,500 | $38k | 5% |
| 202E23000 PAVEMENT REMOVED | 1,876 SY | $18.36 | $34k | 5% |
| 204E13000 EXCAVATION OF SUBGRADE | 631 CY | $48.35 | $31k | 4% |
| 659E00300 TOPSOIL | 433 CY | $62.53 | $27k | 4% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 37 more items below.
| Item | Quantity | R1John R Jurgensen Company | R2Sunesis Construction CO | R3Barrett Paving Materials INC | % of bid |
|---|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 413 CY | $365 | $381 | $300 | 22% |
| 204E30020 GRANULAR MATERIAL, TYPE C | 631 CY | $104 | $88.04 | $90.00 | 9% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 2,476 FT | $23.17 | $22.67 | $23.00 | 8% |
| 442E22300 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 88 CY | $595 | $595 | $475 | 8% |
| 442E22100 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 75 CY | $685 | $685 | $525 | 7% |
| 304E20000 AGGREGATE BASE | 367 CY | $116 | $114 | $125 | 6% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $70,979.55 2 $114,285.83 3 $79,615.80 | 1 LS | $37,500 | $56,217 | $20,000 | 5% |
| 202E23000 PAVEMENT REMOVED | 1,876 SY | $18.36 | $23.18 | $40.00 | 5% |
| 204E13000 EXCAVATION OF SUBGRADE | 631 CY | $48.35 | $14.23 | $45.00 | 4% |
| 659E00300 TOPSOIL | 433 CY | $62.53 | $65.00 | $67.00 | 4% |
| 609E24510 CURB, TYPE 4-C | 455 FT | $54.08 | $58.88 | $50.00 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $23,409 | $40,692 | $46,000 | 3% |
| 203E20000 EMBANKMENT | 930 CY | $25.13 | $2.79 | $50.00 | 3% |
| 203E10000 EXCAVATION | 430 CY | $35.17 | $11.16 | $60.00 | 2% |
| 609E70000 4" CONCRETE MEDIAN | 53 SY | $213 | $200 | $200 | 2% |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER Section 1 - ROADWAY - Totals Awd $194,314.74 2 $130,098.47 3 $264,957.00 | 1 LS | $10,963 | $2,850 | $12,000 | 2% |
| 605E14000 6" BASE PIPE UNDERDRAINS | 250 FT | $43.15 | $21.02 | $30.00 | 2% |
| 644E00104 EDGE LINE, 6" | 1.87 MILE | $5,250 | $7,500 | $5,250 | 1% |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,002 | $1,981 | $2,000 | 1% |
| 204E50000 GEOTEXTILE FABRIC | 1,886 SY | $4.20 | $1.54 | $3.00 | 1% |
| Item | Quantity | R1John R Jurgensen Company | R2Sunesis Construction CO | R3Barrett Paving Materials INC |
|---|---|---|---|---|
| 204E10000 SUBGRADE COMPACTION | 2,129 SY | $2.73 | $3.94 | $6.00 |
| 204E45000 PROOF ROLLING | 2 HOUR | $255 | $272 | $1,000 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 2 SY | $384 | $469 | $150 |
| 659E10000 SEEDING AND MULCHING | 3,905 SY | $1.12 | $3.07 | $1.23 |
| 659E20000 COMMERCIAL FERTILIZER | 0.53 TON | $1,250 | $760 | $915 |
| 659E31000 LIME | 0.81 ACRE | $150 | $50.00 | $100 |
| 659E35000 WATER | 22 MGAL | $1.00 | $50.00 | $1.00 |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $34,023.23 2 $43,614.13 3 $35,702.10 | 1,000 EACH | $1.00 | $1.00 | $1.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 47 FT | $53.75 | $36.34 | $55.00 |
| 611E99700 SPECIAL - GAS VALVE BOX ADJUSTED TO GRADE | 1 EACH | $1,197 | $424 | $750 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET Section 3 - DRAINAGE - Totals Awd $15,273.73 2 $8,737.41 3 $11,135.00 | 1 EACH | $763 | $1,350 | $300 |
| 407E20000 NON-TRACKING TACK COAT | 318 GAL | $5.00 | $5.00 | $4.00 |
| 618E40100 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) Section 4 - PAVEMENT - Totals Awd $339,951.30 2 $344,079.80 3 $292,772.00 | 900 FT | $6.00 | $2.50 | $8.00 |
| 621E00100 RPM | 51 EACH | $78.60 | $78.60 | $78.60 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 80 EACH | $13.25 | $69.74 | $12.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 459 FT | $15.50 | $15.50 | $15.50 |
| 630E08600 SIGN POST REFLECTOR | 17 EACH | $55.00 | $55.00 | $55.00 |
| 630E80100 SIGN, FLAT SHEET | 220.5 SF | $16.00 | $16.00 | $16.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 22 EACH | $15.00 | $15.00 | $15.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $45.00 | $45.00 | $45.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 22 EACH | $29.10 | $20.00 | $20.00 |
| 644E00204 LANE LINE, 6" | 0.74 MILE | $2,505 | $4,000 | $2,505 |
| 644E00300 CENTER LINE | 0.03 MILE | $6,815 | $20,000 | $6,815 |
| 644E00404 CHANNELIZING LINE, 12" | 529 FT | $1.75 | $2.00 | $1.75 |
| 644E00500 STOP LINE | 37 FT | $6.50 | $10.00 | $6.50 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 38 FT | $6.25 | $10.00 | $6.25 |
| 644E01300 LANE ARROW Section 5 - TRAFFIC CONTROL - Totals Awd $31,840.70 2 $42,429.30 3 $31,540.50 | 6 EACH | $150 | $176 | $150 |
| 614E12420 DETOUR SIGNING | 1 LS | $4,848 | $4,315 | $5,000 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (ONE-WAY) | 29 EACH | $12.03 | $9.00 | $11.64 |
| 614E13350 OBJECT MARKER, ONE WAY | 6 EACH | $19.75 | $18.00 | $21.64 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 1.26 MILE | $2,020 | $2,020 | $2,020 |
| 614E24000 WORK ZONE DOTTED LINE, CLASS I | 1,375 FT | $1.00 | $1.00 | $1.00 |
| 616E10000 WATER | 1 MGAL | $100 | $16.41 | $100 |
| 896E00010 PORTABLE NON-INTRUSIVE TRAFFIC SENSOR, CLASS I | 1 SNMT | $963 | $5,800 | $1,000 |
| 896E00021 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $76,525.74 2 $80,069.93 3 $76,335.60 | 1 SNMT | $852 | $1,595 | $900 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,862 | $4,927 | $3,616 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,208 | $12,450 | $10,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →