MOT-Westbrook RSF 03.11
MOT County · est $0.4M
Bid dateThursday, February 19—
Awarded toBARRETT PAVING MATERIALS INC$294,670
MOT County · est $0.4M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E22050 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE B (4 Section 2 - PAVEMENT - Totals Awd $214,136.25 2 $310,130.50 | 584 CY | $240 | $140k | 48% |
| 253E01000 PAVEMENT REPAIR | 280 SY | $145 | $41k | 14% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, 1 | 14,015 SY | $1.95 | $27k | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $18,000 | $18k | 6% |
| 624E10000 MOBILIZATION Section 6 - INCIDENTALS - Totals Awd $38,197.00 2 $25,500.00 | 1 LS | $17,000 | $17k | 6% |
| 611E99654 MANHOLE ADJUSTED TO GRADE Section 1 - DRAINAGE - Totals Awd $16,700.00 2 $42,250.00 | 18 EACH | $800 | $14k | 5% |
| 638E10800 VALVE BOX ADJUSTED TO GRADE Section 3 - WATER WORK - Totals Awd $10,500.00 2 $38,500.00 | 35 EACH | $300 | $11k | 4% |
| 644E00300 CENTER LINE | 0.53 MILE | $8,825 | $5k | 2% |
| 254E01600 PATCHING PLANED SURFACE | 705 SY | $5 | $4k | 1% |
| 644E00630 CROSSWALK LINE, 24" Section 4 - TRAFFIC CONTROL - Totals Awd $10,156.45 2 $10,168.45 | 300 FT | $9.06 | $3k | 1% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 3 more items below.
| Item | Quantity | R1Barrett Paving Materials INC | R2Walls Bros Asphalt CO INC | % of bid |
|---|---|---|---|---|
| 442E22050 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE B (4 Section 2 - PAVEMENT - Totals Awd $214,136.25 2 $310,130.50 | 584 CY | $240 | $330 | 48% |
| 253E01000 PAVEMENT REPAIR | 280 SY | $145 | $252 | 14% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, 1 | 14,015 SY | $1.95 | $2.30 | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $18,000 | $12,000 | 6% |
| 624E10000 MOBILIZATION Section 6 - INCIDENTALS - Totals Awd $38,197.00 2 $25,500.00 | 1 LS | $17,000 | $10,000 | 6% |
| 611E99654 MANHOLE ADJUSTED TO GRADE Section 1 - DRAINAGE - Totals Awd $16,700.00 2 $42,250.00 | 18 EACH | $800 | $2,200 | 5% |
| 638E10800 VALVE BOX ADJUSTED TO GRADE Section 3 - WATER WORK - Totals Awd $10,500.00 2 $38,500.00 | 35 EACH | $300 | $1,100 | 4% |
| 644E00300 CENTER LINE | 0.53 MILE | $8,825 | $8,825 | 2% |
| 254E01600 PATCHING PLANED SURFACE | 705 SY | $5.00 | $10.00 | 1% |
| 644E00630 CROSSWALK LINE, 24" Section 4 - TRAFFIC CONTROL - Totals Awd $10,156.45 2 $10,168.45 | 300 FT | $9.06 | $9.10 | 1% |
| 407E20000 NON-TRACKING TACK COAT, 0.09 GAL/SY | 1,261 GAL | $2.00 | $6.00 | 1% |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 1 EACH | $2,300 | $2,650 | 1% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $2,000 | $2,000 | 1% |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 0.53 MILE | $3,600 | $3,600 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 0.53 MILE | $3,600 | $3,600 | 1% |
| 644E00620 CROSSWALK LINE, 12" | 342 FT | $5.00 | $5.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $1,197 | $1,500 | 0% |
| 644E00500 STOP LINE | 69 FT | $10.00 | $10.00 | 0% |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 69 FT | $6.35 | $6.35 | 0% |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT Section 5 - MAINTENANCE OF TRAFFIC - Totals Awd $4,980.30 2 $4,980.30 | 69 FT | $6.35 | $6.35 | 0% |
| Item | Quantity | R1Barrett Paving Materials INC | R2Walls Bros Asphalt CO INC |
|---|---|---|---|
| 644E00100 EDGE LINE, 4" | 0.06 MILE | $6,020 | $6,020 |
| 614E22100 WORK ZONE EDGE LINE, CLASS I, 4", 642 PAINT | 0.06 MILE | $2,400 | $2,400 |
| 614E22350 WORK ZONE EDGE LINE, CLASS III, 4", 642 PAINT | 0.06 MILE | $2,400 | $2,400 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →