MER-FT RECOVERY SIDEWALKS SA22
MER County · est $1.0M
Bid dateThursday, January 29—
Awarded toJUTTE EXCAVATING INC$888,655.46
MER County · est $1.0M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 608E10000 4" CONCRETE WALK | 31,891 SF | $7 | $223k | 25% |
| 625E10481 LIGHT POLE, AESTHETIC, AS PER PLAN, (SIGNIFY) | 8 EACH | $8,000 | $64k | 7% |
| 625E27551 LUMINAIRE, DECORATIVE, AS PER PLAN IES-III-M, LED, | 10 EACH | $5,000 | $50k | 6% |
| 452E10011 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 574 SY | $66 | $38k | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $34,000 | $34k | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $30,000 | $30k | 3% |
| 624E10000 MOBILIZATION Section 10 - INCIDENTALS - Totals Awd $112,500.00 2 $48,800.00 3 $114,528.50 4 $160,500.00 | 1 LS | $28,000 | $28k | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $27,000 | $27k | 3% |
| 638E10300 FIRE HYDRANT EXTENDED AND ADJUSTED TO GRADE | 5 EACH | $5,000 | $25k | 3% |
| 625E14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP | 8 EACH | $3,000 | $24k | 3% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 83 more items below.
| Item | Quantity | R1Jutte Excavating INC | R2D L Smith Concrete LLC | R3Brumbaugh Construction INC | R4L J Deweese CO INC | % of bid |
|---|---|---|---|---|---|---|
| 608E10000 4" CONCRETE WALK | 31,891 SF | $7.00 | $9.00 | $8.00 | $9.00 | 32% |
| 625E10481 LIGHT POLE, AESTHETIC, AS PER PLAN, (SIGNIFY) | 8 EACH | $8,000 | $5,700 | $6,105 | $5,500 | 9% |
| 625E27551 LUMINAIRE, DECORATIVE, AS PER PLAN IES-III-M, LED, | 10 EACH | $5,000 | $3,300 | $3,580 | $3,300 | 7% |
| 452E10011 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 574 SY | $66.00 | $100 | $75.00 | $125 | 5% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $34,000 | $7,800 | $11,500 | $25,000 | 5% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $30,000 | $4,000 | $24,000 | $10,000 | 4% |
| 624E10000 MOBILIZATION Section 10 - INCIDENTALS - Totals Awd $112,500.00 2 $48,800.00 3 $114,528.50 4 $160,500.00 | 1 LS | $28,000 | $15,000 | $45,029 | $58,000 | 4% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $27,000 | $15,000 | $8,000 | $12,500 | 4% |
| 638E10300 FIRE HYDRANT EXTENDED AND ADJUSTED TO GRADE | 5 EACH | $5,000 | $1,650 | $750 | $2,000 | 4% |
| 625E14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP | 8 EACH | $3,000 | $2,600 | $2,525 | $7,500 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $23,500 | $11,000 | $50,000 | $65,000 | 3% |
| 452E13011 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P, | 232 SY | $83.00 | $120 | $95.00 | $170 | 3% |
| 203E10000 EXCAVATION | 425 CY | $40.00 | $85.00 | $75.00 | $40.00 | 2% |
| 630E97700 SIGNING, MISC.:RECTANGULAR RAPID FLASHING BEACON ( | 2 EACH | $7,500 | $6,250 | $7,900 | $6,500 | 2% |
| 625E10481 LIGHT POLE, AESTHETIC, AS PER PLAN, RRFB | 2 EACH | $7,000 | $5,700 | $6,100 | $5,500 | 2% |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $13,000 | $13,000 | $6,750 | $8,000 | 2% |
| 659E00300 TOPSOIL | 483 CY | $26.00 | $62.00 | $75.00 | $70.00 | 2% |
| 202E23000 PAVEMENT REMOVED | 917 SY | $12.00 | $16.00 | $15.00 | $27.00 | 2% |
| 611E98390 CATCH BASIN, NO. 7 | 3 EACH | $3,500 | $2,250 | $2,750 | $5,000 | 2% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $61,020.65 2 $101,913.75 3 $83,786.50 4 $80,508.50 | 10,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| Item | Quantity | R1Jutte Excavating INC | R2D L Smith Concrete LLC | R3Brumbaugh Construction INC | R4L J Deweese CO INC |
|---|---|---|---|---|---|
| 202E30000 WALK REMOVED | 395 SF | $2.00 | $4.00 | $8.00 | $7.00 |
| 202E32500 CURB AND GUTTER REMOVED | 163 FT | $5.00 | $10.00 | $20.00 | $25.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 45 FT | $5.00 | $25.00 | $18.00 | $45.00 |
| 202E35200 PIPE REMOVED, OVER 24" DIAMETER | 10 FT | $5.00 | $25.00 | $20.00 | $65.00 |
| 202E58100 CATCH BASIN REMOVED | 2 EACH | $150 | $650 | $800 | $900 |
| 203E20000 EMBANKMENT | 242 CY | $30.00 | $68.00 | $75.00 | $40.00 |
| 608E52000 CURB RAMP | 2,146 SF | $2.00 | $25.00 | $22.00 | $28.00 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $500 | $3,500 | $3,650 | $3,000 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $500 | $3,500 | $3,650 | $3,000 |
| 653E10000 TOPSOIL FURNISHED AND PLACED | 69 CY | $26.00 | $65.00 | $75.00 | $100 |
| 690E50350 SPECIAL - MAILBOX REMOVED AND RESET Section 1 - ROADWAY - Totals Awd $300,567.00 2 $431,392.00 3 $415,895.00 4 $436,261.00 | 14 EACH | $200 | $150 | $305 | $250 |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 5,449 SY | $1.75 | $5.75 | $2.00 | $2.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 217 SY | $1.75 | $5.75 | $1.75 | $2.00 |
| 659E15000 INTER-SEEDING | 217 SY | $1.75 | $5.75 | $1.75 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.6 TON | $760 | $260 | $850 | $1,000 |
| 659E31000 LIME | 0.9 ACRE | $50.00 | $55.00 | $50.00 | $5.00 |
| 659E35000 WATER | 24 MGAL | $50.00 | $18.00 | $50.00 | $5.00 |
| 670E00500 SLOPE EROSION PROTECTION | 618 SY | $4.80 | $8.50 | $5.50 | $6.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,500 | $2,000 | $3,000 | $3,500 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $8,000 | $7,250 | $11,000 | $9,000 |
| 611E00900 6" CONDUIT, TYPE B | 23 FT | $20.00 | $35.00 | $54.00 | $80.00 |
| 611E01200 6" CONDUIT, TYPE D | 63 FT | $20.00 | $35.00 | $65.00 | $80.00 |
| 611E01800 8" CONDUIT, TYPE B | 16 FT | $30.00 | $38.00 | $67.00 | $125 |
| 611E02000 8" CONDUIT, TYPE C | 91 FT | $30.00 | $38.00 | $47.00 | $105 |
| 611E04900 12" CONDUIT, TYPE D | 119 FT | $40.00 | $46.00 | $49.00 | $125 |
| 611E07400 18" CONDUIT, TYPE B | 3 FT | $45.00 | $50.00 | $380 | $350 |
| 611E10400 24" CONDUIT, TYPE B | 4 FT | $70.00 | $58.00 | $400 | $400 |
| 611E13600 30" CONDUIT, TYPE C | 10 FT | $100 | $72.00 | $200 | $300 |
| 611E97400 CONDUIT, MISC.:TYPE B FOR DRAINAGE DISCHARGE CONTI | 20 FT | $10.00 | $67.00 | $13.00 | $25.00 |
| 611E97400 CONDUIT, MISC.:TYPE C FOR DRAINAGE DISCHARGE CONTI | 20 FT | $10.00 | $67.00 | $13.00 | $25.00 |
| 611E97400 CONDUIT, MISC.:TYPE E FOR DRAINAGE DISCHARGE CONTI | 20 FT | $10.00 | $67.00 | $13.00 | $25.00 |
| 611E97400 CONDUIT, MISC.:TYPE F FOR DRAINAGE DISCHARGE CONTI | 20 FT | $10.00 | $67.00 | $13.00 | $25.00 |
| 611E98391 CATCH BASIN, NO. 7, AS PER PLAN | 1 EACH | $3,500 | $2,250 | $3,400 | $5,000 |
| 611E98470 CATCH BASIN, NO. 2-2B | 2 EACH | $3,250 | $2,450 | $2,000 | $3,000 |
| 611E98511 CATCH BASIN, NO. 2-3, AS PER PLAN | 1 EACH | $4,500 | $3,150 | $3,250 | $5,000 |
| 611E99574 MANHOLE, NO. 3 | 1 EACH | $8,000 | $4,150 | $3,250 | $6,500 |
| 611E99654 MANHOLE ADJUSTED TO GRADE Section 3 - DRAINAGE - Totals Awd $45,155.00 2 $41,497.00 3 $44,747.00 4 $79,460.00 | 1 EACH | $250 | $1,285 | $300 | $1,000 |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 9 CY | $925 | $305 | $1,070 | $1,000 |
| 304E20000 AGGREGATE BASE | 89 CY | $74.00 | $72.00 | $86.00 | $125 |
| 407E20000 NON-TRACKING TACK COAT | 9 GAL | $6.00 | $42.00 | $25.00 | $50.00 |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 3 CY | $1,590 | $360 | $1,070 | $1,000 |
| 441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (5 CY | $1,035 | $320 | $1,090 | $1,000 |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN Section 4 - PAVEMENT - Totals Awd $86,940.00 2 $106,416.00 3 $98,920.00 4 $149,545.00 | 163 FT | $30.00 | $55.00 | $47.00 | $60.00 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE Section 5 - WATER WORK - Totals Awd $25,900.00 2 $12,360.00 3 $5,550.00 4 $12,100.00 | 6 EACH | $150 | $685 | $300 | $350 |
| 611E99900 DRAINAGE STRUCTURE, MISC.:CLEANOUT ADJUSTED TO GRA Section 6 - SANITARY SEWER - Totals Awd $150.00 2 $1,150.00 3 $300.00 4 $350.00 | 1 EACH | $150 | $1,150 | $300 | $350 |
| 611E00400 4" CONDUIT, TYPE E | 140 FT | $5.00 | $6.00 | $15.00 | $12.00 |
| 625E00451 CONNECTION, FUSED PULL APART, AS PER PLAN | 30 EACH | $10.00 | $125 | $147 | $150 |
| 625E00460 CONNECTION, UNFUSED PULL APART | 10 EACH | $8.00 | $125 | $158 | $150 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 6 EACH | $80.00 | $120 | $147 | $170 |
| 625E22990 NO. 6 AWG 600 VOLT DISTRIBUTION CABLE | 2,646 FT | $2.00 | $4.00 | $3.50 | $3.00 |
| 625E23304 NO. 8 AWG 600 VOLT DISTRIBUTION CABLE | 3,204 FT | $3.00 | $3.50 | $3.00 | $2.50 |
| 625E23410 NO. 12 AWG POLE AND BRACKET CABLE | 1,308 FT | $2.00 | $2.50 | $1.00 | $2.50 |
| 625E25408 CONDUIT, 2", 725.051 | 452 FT | $10.00 | $14.00 | $4.00 | $6.00 |
| 625E25504 CONDUIT, 3", 725.051 | 150 FT | $12.00 | $17.00 | $6.00 | $8.00 |
| 625E25604 CONDUIT, 4", 725.051 | 85 FT | $14.00 | $19.00 | $10.50 | $9.00 |
| 625E25909 CONDUIT, JACKED OR DRILLED, 725.052, AS PER PLAN, | 69 FT | $15.00 | $48.00 | $25.00 | $45.00 |
| 625E25909 CONDUIT, JACKED OR DRILLED, 725.052, AS PER PLAN, | 171 FT | $17.00 | $55.50 | $27.00 | $65.00 |
| 625E25909 CONDUIT, JACKED OR DRILLED, 725.052, AS PER PLAN, | 81 FT | $20.00 | $60.00 | $32.00 | $50.00 |
| 625E29000 TRENCH | 687 FT | $10.00 | $15.00 | $17.00 | $11.00 |
| 625E30520 PULL BOX, 725.06, SIZE 7 | 7 EACH | $1,000 | $1,750 | $2,750 | $900 |
| 625E32000 GROUND ROD | 10 EACH | $100 | $300 | $210 | $300 |
| 625E34001 POWER SERVICE, AS PER PLAN | 2 EACH | $3,000 | $11,500 | $6,500 | $13,500 |
| 625E36010 UNDERGROUND WARNING MARKING TAPE | 687 FT | $1.00 | $3.50 | $0.50 | $2.00 |
| 632E69320 POWER CABLE, 3 CONDUCTOR, NO. 2 AWG Section 7 - LIGHTING - Totals Awd $193,305.00 2 $212,271.00 3 $195,161.00 4 $233,628.00 | 133 FT | $12.00 | $16.00 | $17.00 | $4.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 181 FT | $15.00 | $18.00 | $10.00 | $12.00 |
| 630E80100 SIGN, FLAT SHEET | 106 SF | $25.00 | $19.00 | $28.00 | $25.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 3 EACH | $50.00 | $24.00 | $21.00 | $20.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 32 EACH | $100 | $50.00 | $47.00 | $60.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 1 EACH | $50.00 | $30.00 | $26.00 | $40.00 |
| 630E86010 REMOVAL OF GROUND MOUNTED POST SUPPORT AND REERECT | 20 EACH | $100 | $72.00 | $68.00 | $115 |
| 644E00100 EDGE LINE, 4" | 0.03 MILE | $11,204 | $11,500 | $11,800 | $12,000 |
| 644E00400 CHANNELIZING LINE, 8" | 78 FT | $3.00 | $3.50 | $3.00 | $3.00 |
| 644E00500 STOP LINE | 70 FT | $12.75 | $13.50 | $13.00 | $13.00 |
| 644E00620 CROSSWALK LINE, 12" | 409 FT | $6.35 | $7.00 | $7.00 | $7.00 |
| 644E00630 CROSSWALK LINE, 24" | 380 FT | $11.45 | $12.00 | $12.00 | $12.00 |
| 644E01300 LANE ARROW | 2 EACH | $200 | $215 | $210 | $225 |
| 644E20800 YIELD LINE | 38 FT | $25.00 | $27.00 | $26.00 | $30.00 |
| 644E30000 REMOVAL OF PAVEMENT MARKING Section 8 - TRAFFIC CONTROL - Totals Awd $23,453.81 2 $22,406.00 3 $21,042.00 4 $22,641.00 | 142 FT | $20.62 | $25.00 | $21.00 | $21.00 |
| 625E14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP, RRFB | 2 EACH | $3,000 | $2,500 | $2,500 | $7,400 |
| 625E32000 GROUND ROD, RRFB | 2 EACH | $100 | $300 | $210 | $270 |
| 632E20750 ACCESSIBLE PEDESTRIAN PUSHBUTTON, BLACK | 2 EACH | $750 | $858 | $750 | $900 |
| 632E40300 SIGNAL CABLE, 3 CONDUCTOR, NO. 14 AWG | 490 FT | $3.00 | $3.00 | $3.00 | $3.00 |
| 632E40500 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG Section 9 - TRAFFIC SIGNALS - Totals Awd $39,664.00 2 $34,429.00 3 $38,382.00 4 $44,228.50 | 498 FT | $3.00 | $3.50 | $4.00 | $3.25 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →