Figure 0.1 · BRIEFING
BID #260017 · ODOTRESULT · awarded Jan 15

HAM-SR 128-00.00

HAM County · est $2.5M

Bid dateThursday, January 15
Awarded toBARRETT PAVING MATERIALS INC$2.75M
read → connected → answeredcassandri

Project scope

Bid form · ODOT

53ITEMS
  • Maintaining Traffic26%
  • Pavement Marking17%
  • Guardrail & Barrier11%
  • Erosion & Landscaping8%
  • Earthwork6%
  • Removal & Demolition6%
  • Other26%

Top items by winning bid

ItemQtyUnit priceExtended%
442E10001 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A (4,543 CY$245$1.11M40%
253E02000 PAVEMENT REPAIR, (A)1,000 CY$600$600k22%
254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" DEPTH109,016 SY$2.65$289k10%
253E02000 PAVEMENT REPAIR, (B)365 CY$500$183k7%
614E11000 MAINTAINING TRAFFIC1 LS$100,000$100k4%
617E10100 COMPACTED AGGREGATE366 CY$190$70k3%
624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $164,500.00 2 $515,409.001 LS$50,000$50k2%
644E00104 EDGE LINE, 6"11.13 MILE$4,400$49k2%
407E20000 NON-TRACKING TACK COAT9,812 GAL$4$39k1%
644E00300 CENTER LINE5.81 MILE$5,800$34k1%

Per-bidder unit pricing

ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 33 more items below.

Rank 1Barrett Paving Materials INC$2.75MRank 2John R Jurgensen Company$3.41M
ItemQuantityR1Barrett Paving Materials INCR2John R Jurgensen Company
442E10001 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A (4,543 CY$245$265
253E02000 PAVEMENT REPAIR, (A)1,000 CY$600$950
254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" DEPTH109,016 SY$2.65$1.35
253E02000 PAVEMENT REPAIR, (B)365 CY$500$515
614E11000 MAINTAINING TRAFFIC1 LS$100,000$332,606
617E10100 COMPACTED AGGREGATE366 CY$190$164
624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $164,500.00 2 $515,409.001 LS$50,000$162,500
644E00104 EDGE LINE, 6"11.13 MILE$4,400$4,400
407E20000 NON-TRACKING TACK COAT9,812 GAL$4.00$4.00
644E00300 CENTER LINE5.81 MILE$5,800$5,800
621E00100 RPM430 EACH$50.00$41.25
606E26150 ANCHOR ASSEMBLY, MGS TYPE E8 EACH$2,600$2,600
614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST200 HOUR$95.00$139
611E98630 CATCH BASIN ADJUSTED TO GRADE8 EACH$2,000$1,469
614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT11.13 MILE$1,398$1,398
659E00300 TOPSOIL222 CY$64.00$110
614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT5.81 MILE$2,090$2,090
606E15050 GUARDRAIL, TYPE MGS425 FT$28.50$28.50
618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) Section 4 - PAVEMENT - Totals Awd $2,319,067.40 2 $2,614,341.271.61 MILE$7,000$4,250
103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM1 LS$10,000$10,427
Show all 53 line items
ItemQuantityR1Barrett Paving Materials INCR2John R Jurgensen Company
202E38000 GUARDRAIL REMOVED25 FT$11.00$11.00
202E42010 ANCHOR ASSEMBLY REMOVED, TYPE E7 EACH$125$125
202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T1 EACH$75.00$75.00
204E10000 SUBGRADE COMPACTION5 SY$10.00$74.50
608E10000 4" CONCRETE WALK48 SF$50.00$86.02
608E52000 CURB RAMP86 SF$85.00$79.12
608E53020 DETECTABLE WARNING Section 1 - ROADWAY - Totals Awd $45,297.50 2 $47,403.2828 SF$50.00$70.00
659E10000 SEEDING AND MULCHING2,000 SY$1.70$1.70
659E20000 COMMERCIAL FERTILIZER0.27 TON$975$975
659E31000 LIME0.41 ACRE$75.00$75.00
659E35000 WATER11.1 MGAL$1.00$1.00
832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $18,913.10 2 $29,231.661,000 EACH$1.00$1.00
611E99654 MANHOLE ADJUSTED TO GRADE Section 3 - DRAINAGE - Totals Awd $20,500.00 2 $17,492.663 EACH$1,500$1,914
253E01000 PAVEMENT REPAIR5 SY$675$150
254E01600 PATCHING PLANED SURFACE1,092 SY$4.00$4.47
617E20000 SHOULDER PREPARATION6,594 SY$1.00$1.69
617E25000 WATER7 MGAL$35.00$7.92
621E54000 RAISED PAVEMENT MARKER REMOVED430 EACH$7.50$12.56
626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL)8 EACH$10.00$10.00
644E00400 CHANNELIZING LINE, 8"1,712 FT$1.50$1.50
644E00500 STOP LINE262 FT$6.75$6.75
644E00620 CROSSWALK LINE, 12"247 FT$6.50$6.50
644E00700 TRANSVERSE/DIAGONAL LINE, 24"672 FT$5.70$5.70
644E01100 SCHOOL SYMBOL MARKING, 72"2 EACH$650$650
644E01300 LANE ARROW Section 5 - TRAFFIC CONTROL - Totals Awd $122,172.40 2 $120,585.7029 EACH$125$125
614E18600 PORTABLE CHANGEABLE MESSAGE SIGN8 SNMT$895$895
614E23690 WORK ZONE CHANNELIZING LINE, CLASS III, 12", 642 P1,712 FT$0.80$0.80
614E25620 WORK ZONE TRANSVERSE/DIAGONAL LINE, CLASS III, 642672 FT$3.25$3.25
614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT262 FT$4.35$4.35
614E27260 WORK ZONE CROSSWALK LINE, CLASS III, 24", 642 PAIN247 FT$4.35$4.35
614E30650 WORK ZONE ARROW, CLASS III, 642 PAINT29 EACH$30.00$30.00
614E31740 WORK ZONE SCHOOL SYMBOL MARKING, 72", CLASS III, 6 Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $61,210.39 2 $69,926.392 EACH$355$355
623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P1 LS$4,500$9,876

Project details

Description
HAM-SR 128-00.00
Type of work
Pavement

How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →