ATB-/TRU Culverts FY2026
ATB County · est $0.6M
Bid dateThursday, April 9—
Awarded toBOG CONSTRUCTION INC$545,956
ATB County · est $0.6M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 129 CY | $540 | $70k | 13% |
| 611E53200 48" X 76" CONDUIT, TYPE A, 706.04 Section 3 - DRAINAGE - Totals Awd $163,758.00 2 $220,371.00 3 $251,776.25 4 $277,875.00 5 $348,550.00 | 80 FT | $810 | $65k | 12% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 109 CY | $420 | $46k | 8% |
| 602E20000 CONCRETE MASONRY | 59 CY | $775 | $46k | 8% |
| 611E19200 42" CONDUIT, TYPE A, 706.02 OR 707.01/707.02 (0.06 | 143 FT | $266 | $38k | 7% |
| 202E35200 PIPE REMOVED, OVER 24" DIAMETER | 235 FT | $125 | $29k | 5% |
| 614E12420 DETOUR SIGNING | 1 LS | $25,000 | $25k | 5% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, (T=3") | 920 SY | $25 | $23k | 4% |
| 203E10000 EXCAVATION | 628 CY | $30 | $19k | 3% |
| 304E20000 AGGREGATE BASE, (T=6") | 122 CY | $135 | $16k | 3% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 40 more items below.
| Item | Quantity | R1Bog Construction INC | R2Rudzik Excavating INC | R3Eclipse CO LLC | R4S E T INC | R5Union Industrial Contractors INC | % of bid |
|---|---|---|---|---|---|---|---|
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 129 CY | $540 | $461 | $495 | $425 | $450 | 15% |
| 611E53200 48" X 76" CONDUIT, TYPE A, 706.04 Section 3 - DRAINAGE - Totals Awd $163,758.00 2 $220,371.00 3 $251,776.25 4 $277,875.00 5 $348,550.00 | 80 FT | $810 | $1,005 | $682 | $850 | $1,100 | 13% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 109 CY | $420 | $460 | $468 | $425 | $400 | 10% |
| 602E20000 CONCRETE MASONRY | 59 CY | $775 | $1,020 | $1,629 | $1,100 | $1,500 | 10% |
| 611E19200 42" CONDUIT, TYPE A, 706.02 OR 707.01/707.02 (0.06 | 143 FT | $266 | $295 | $208 | $425 | $500 | 8% |
| 202E35200 PIPE REMOVED, OVER 24" DIAMETER | 235 FT | $125 | $51.50 | $109 | $35.00 | $225 | 6% |
| 614E12420 DETOUR SIGNING | 1 LS | $25,000 | $25,450 | $24,691 | $22,000 | $22,500 | 5% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, (T=3") | 920 SY | $25.00 | $22.00 | $22.00 | $21.00 | $40.00 | 5% |
| 203E10000 EXCAVATION | 628 CY | $30.00 | $50.00 | $31.75 | $25.00 | $70.00 | 4% |
| 304E20000 AGGREGATE BASE, (T=6") | 122 CY | $135 | $120 | $112 | $90.00 | $150 | 3% |
| 202E23000 PAVEMENT REMOVED | 603 SY | $25.00 | $12.75 | $23.50 | $17.00 | $30.00 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $15,000 | $6,519 | $9,613 | $35,000 | $15,000 | 3% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $49,500.00 2 $53,683.56 3 $101,574.00 4 $141,000.00 5 $70,000.00 | 1 LS | $15,000 | $35,000 | $71,153 | $50,000 | $20,000 | 3% |
| 659E10000 SEEDING AND MULCHING | 1,741 SY | $8.00 | $3.00 | $4.00 | $4.00 | $5.00 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,000 | $6,000 | $8,720 | $7,000 | $8,000 | 2% |
| 601E32010 ROCK CHANNEL PROTECTION, TYPE A WITH AGGREGATE FIL Section 2 - EROSION CONTROL - Totals Awd $42,796.00 2 $47,634.69 3 $45,837.11 4 $51,280.00 5 $91,120.00 | 64.4 CY | $125 | $225 | $178 | $175 | $350 | 2% |
| 203E20000 EMBANKMENT | 255 CY | $30.00 | $66.00 | $17.00 | $23.00 | $90.00 | 2% |
| 659E00300 TOPSOIL | 193 CY | $35.00 | $25.00 | $54.25 | $80.00 | $85.00 | 1% |
| 690E91000 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $5,500 | $5,000 | $3,908 | $6,000 | $5,000 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $4,500 | $5,325 | $2,324 | $40,000 | $15,000 | 1% |
| Item | Quantity | R1Bog Construction INC | R2Rudzik Excavating INC | R3Eclipse CO LLC | R4S E T INC | R5Union Industrial Contractors INC |
|---|---|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND CULVERT | 1 LS | $2,000 | $4,000 | $2,863 | $12,000 | $3,000 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND CULVERT | 1 LS | $2,000 | $1,600 | $867 | $6,000 | $3,000 |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN, AROUND CULVERT | 1 LS | $2,000 | $2,300 | $867 | $6,000 | $3,000 |
| 202E20010 HEADWALL REMOVED (ATB- 45-17.196) | 2 EACH | $750 | $750 | $733 | $800 | $2,000 |
| 202E20010 HEADWALL REMOVED (ATB-193-11.140) | 2 EACH | $750 | $1,500 | $733 | $1,800 | $2,500 |
| 202E20010 HEADWALL REMOVED (TRU-193-23.897) | 2 EACH | $750 | $1,500 | $733 | $1,800 | $2,500 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 12 FT | $50.00 | $30.00 | $49.00 | $35.00 | $150 |
| 204E10000 SUBGRADE COMPACTION | 728 SY | $4.00 | $2.50 | $1.75 | $3.00 | $5.00 |
| 690E98400 SPECIAL - SURVEY CONTROL VERIFICATION (ATB-45-17. | 1 LS | $4,000 | $1,330 | $1,100 | $3,000 | $1,500 |
| 690E98400 SPECIAL - SURVEY CONTROL VERIFICATION (ATB-193-11. | 1 LS | $2,500 | $1,330 | $1,100 | $3,000 | $1,500 |
| 690E98400 SPECIAL - SURVEY CONTROL VERIFICATION (TRU-193-23. Section 1 - ROADWAY - Totals Awd $99,452.00 2 $94,590.75 3 $82,120.00 4 $90,445.00 5 $175,815.00 | 1 LS | $2,500 | $1,330 | $1,100 | $3,000 | $1,500 |
| 601E11000 RIPRAP, TYPE D | 9 SY | $250 | $490 | $308 | $215 | $900 |
| 601E11001 RIPRAP, TYPE D, AS PER PLAN | 14 SY | $200 | $440 | $182 | $215 | $800 |
| 601E32110 ROCK CHANNEL PROTECTION, TYPE B WITH AGGREGATE FIL | 25 CY | $100 | $230 | $178 | $175 | $450 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 6 CY | $150 | $289 | $327 | $230 | $600 |
| 659E20000 COMMERCIAL FERTILIZER | 0.23 TON | $1,000 | $500 | $880 | $2,500 | $5,000 |
| 659E31000 LIME | 0.36 ACRE | $150 | $10.00 | $1.00 | $1,200 | $3,000 |
| 659E35000 WATER | 9 MGAL | $1.00 | $0.01 | $0.50 | $35.00 | $50.00 |
| 832E30000 EROSION CONTROL | 4,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 836E10030 SEEDING AND EROSION CONTROL WITH TURF REINFORCING | 132 SY | $10.00 | $7.00 | $7.75 | $12.00 | $20.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING (ATB-193-11.140) | 1 LS | $2,500 | $13,000 | $20,040 | $20,000 | $25,000 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING (ATB-45-17.196) | 1 LS | $2,500 | $1,250 | $23,574 | $35,000 | $25,000 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING (TRU-193-23.897) | 1 LS | $2,500 | $15,400 | $20,696 | $20,000 | $25,000 |
| 605E31100 AGGREGATE DRAINS | 193 FT | $15.00 | $24.00 | $10.25 | $20.00 | $50.00 |
| 611E00900 6" CONDUIT, TYPE B | 60 FT | $20.00 | $13.25 | $26.25 | $40.00 | $75.00 |
| 611E01400 6" CONDUIT, TYPE E | 60 FT | $20.00 | $8.55 | $17.00 | $15.00 | $75.00 |
| 611E01500 6" CONDUIT, TYPE F | 60 FT | $20.00 | $4.60 | $17.00 | $15.00 | $75.00 |
| 611E04600 12" CONDUIT, TYPE C | 12 FT | $100 | $145 | $126 | $95.00 | $200 |
| 407E20000 NON-TRACKING TACK COAT | 151 GAL | $5.00 | $2.00 | $11.00 | $3.00 | $5.00 |
| 408E10001 PRIME COAT, AS PER PLAN, (@ 0.40 GAL/SY) | 92 GAL | $10.00 | $3.00 | $22.00 | $4.00 | $5.00 |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN, (T=1") Section 4 - PAVEMENT - Totals Awd $157,665.00 2 $147,047.00 3 $154,876.50 4 $133,171.00 5 $159,990.00 | 9 CY | $120 | $220 | $275 | $100 | $225 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 45 FT | $50.00 | $54.00 | $53.50 | $40.00 | $50.00 |
| 630E80100 SIGN, FLAT SHEET, 730.20 | 6 SF | $60.00 | $62.00 | $62.00 | $130 | $56.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $50.00 | $19.00 | $18.25 | $30.00 | $17.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $50.00 | $25.00 | $24.50 | $30.00 | $23.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.17 MILE | $7,500 | $5,200 | $5,170 | $10,000 | $4,700 |
| 642E00300 CENTER LINE, TYPE 1 Section 5 - TRAFFIC CONTROL - Totals Awd $4,685.00 2 $4,190.00 3 $4,157.50 4 $6,080.00 5 $3,841.00 | 0.08 MILE | $7,500 | $5,200 | $5,170 | $21,000 | $4,700 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 32 HOUR | $50.00 | $1.00 | $88.00 | $85.00 | $100 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $28,100.00 2 $25,483.00 3 $34,107.25 4 $28,720.00 5 $28,700.00 | 10 CY | $150 | $0.10 | $660 | $400 | $300 |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $500 | $140 | $1,628 | $1,500 | $2,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →