ASD-SR 60-14.97
ASD County · est $0.4M
Bid dateThursday, April 9—
Awarded toADENA CORPORATION$389,830.31
ASD County · est $0.4M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E53500 63" X 98" CONDUIT, TYPE A, 706.04 | 112 FT | $1,262 | $141k | 36% |
| 442E22001 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 Section 4 - PAVEMENT - Totals Awd $74,499.29 2 $75,450.66 3 $65,703.51 4 $77,198.87 5 $72,129.00 | 42 CY | $681.68 | $29k | 7% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 82 CY | $325.79 | $27k | 7% |
| 203E20000 EMBANKMENT | 773 CY | $25.48 | $20k | 5% |
| 602E20000 CONCRETE MASONRY Section 7 - STRUCTURE 20 FOOT SPAN AND UNDER (ASD-60 - Totals Awd $30,429.70 2 $20,318.57 3 $20,961.51 4 $28,231.26 5 $33,013.00 | 5.27 CY | $3,236 | $17k | 4% |
| 202E11001 STRUCTURE REMOVED, AS PER PLAN | 1 LS | $14,589 | $15k | 4% |
| 624E10000 MOBILIZATION Section 8 - INCIDENTALS - Totals Awd $36,438.80 2 $45,263.44 3 $52,700.00 4 $58,424.92 5 $50,900.00 | 1 LS | $13,425 | $13k | 3% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $13,375 | $13k | 3% |
| 304E20000 AGGREGATE BASE | 111 CY | $99.57 | $11k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $9,881 | $10k | 3% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 29 more items below.
| Item | Quantity | R1Adena Corporation | R2Eius Company | R3Brennstuhl Construction INC | R4Eclipse CO LLC | R5Rietschlin Construction INC | % of bid |
|---|---|---|---|---|---|---|---|
| 611E53500 63" X 98" CONDUIT, TYPE A, 706.04 | 112 FT | $1,262 | $1,098 | $1,140 | $1,016 | $1,350 | 40% |
| 442E22001 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 Section 4 - PAVEMENT - Totals Awd $74,499.29 2 $75,450.66 3 $65,703.51 4 $77,198.87 5 $72,129.00 | 42 CY | $682 | $578 | $416 | $543 | $594 | 8% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 82 CY | $326 | $315 | $311 | $422 | $324 | 8% |
| 203E20000 EMBANKMENT | 773 CY | $25.48 | $39.39 | $39.10 | $30.50 | $20.00 | 6% |
| 602E20000 CONCRETE MASONRY Section 7 - STRUCTURE 20 FOOT SPAN AND UNDER (ASD-60 - Totals Awd $30,429.70 2 $20,318.57 3 $20,961.51 4 $28,231.26 5 $33,013.00 | 5.27 CY | $3,236 | $3,172 | $1,650 | $2,304 | $1,900 | 5% |
| 202E11001 STRUCTURE REMOVED, AS PER PLAN | 1 LS | $14,589 | $5,160 | $6,706 | $10,112 | $47,100 | 4% |
| 624E10000 MOBILIZATION Section 8 - INCIDENTALS - Totals Awd $36,438.80 2 $45,263.44 3 $52,700.00 4 $58,424.92 5 $50,900.00 | 1 LS | $13,425 | $12,999 | $11,070 | $34,176 | $30,000 | 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $13,375 | $3,602 | $12,264 | $16,088 | $23,000 | 4% |
| 304E20000 AGGREGATE BASE | 111 CY | $99.57 | $154 | $133 | $109 | $113 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $9,881 | $2,271 | $6,706 | $5,676 | $500 | 3% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 60 CY | $132 | $227 | $153 | $159 | $162 | 2% |
| 611E99574 MANHOLE, NO. 3 Section 3 - DRAINAGE - Totals Awd $160,157.84 2 $165,822.22 3 $153,924.18 4 $146,211.15 5 $180,420.00 | 2 EACH | $3,509 | $7,480 | $3,265 | $5,739 | $4,900 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $6,299 | $3,480 | $26,802 | $32,500 | $8,000 | 2% |
| 611E07600 18" CONDUIT, TYPE C | 110 FT | $55.36 | $139 | $91.41 | $88.35 | $100 | 2% |
| 614E12420 DETOUR SIGNING | 1 LS | $5,877 | $6,500 | $5,225 | $7,772 | $5,200 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,531 | $5,063 | $6,394 | $6,454 | $7,000 | 2% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $26,276.53 2 $42,681.17 3 $45,560.55 4 $36,738.56 5 $33,303.60 | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (VARIES 0" TO 3 | 160 SY | $30.93 | $26.25 | $18.22 | $11.13 | $27.00 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,603 | $3,180 | $13,530 | $3,622 | $5,000 | 1% |
| 601E11000 RIPRAP, TYPE D | 16 SY | $287 | $724 | $174 | $478 | $310 | 1% |
| Item | Quantity | R1Adena Corporation | R2Eius Company | R3Brennstuhl Construction INC | R4Eclipse CO LLC | R5Rietschlin Construction INC |
|---|---|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 327 SY | $8.07 | $6.58 | $10.26 | $23.70 | $15.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 48 FT | $4.02 | $6.45 | $69.85 | $75.69 | $53.00 |
| 202E75000 FENCE REMOVED | 55 FT | $7.01 | $5.16 | $15.24 | $12.14 | $30.00 |
| 203E10000 EXCAVATION | 51 CY | $18.92 | $12.90 | $32.88 | $10.74 | $65.00 |
| 204E10000 SUBGRADE COMPACTION | 395 SY | $3.90 | $2.58 | $2.83 | $2.08 | $5.00 |
| 623E38500 MONUMENT ASSEMBLY, TYPE C | 2 EACH | $1,886 | $1,994 | $605 | $1,018 | $1,525 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $1,151 | $1,728 | $1,639 | $2,300 | $1,005 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND Section 1 - ROADWAY - Totals Awd $52,379.22 2 $50,953.53 3 $78,560.15 4 $86,244.32 5 $90,009.00 | 1 LS | $1,151 | $1,728 | $1,639 | $2,300 | $1,005 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $125 | $63.00 | $166 | $60.00 | $150 |
| 659E00300 TOPSOIL | 150 CY | $23.88 | $51.86 | $116 | $65.00 | $48.00 |
| 659E10000 SEEDING AND MULCHING | 1,349 SY | $2.86 | $2.52 | $4.31 | $2.40 | $3.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 67 SY | $1.00 | $2.10 | $6.82 | $2.00 | $3.00 |
| 659E15000 INTER-SEEDING | 67 SY | $1.00 | $0.74 | $6.82 | $0.70 | $3.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.19 TON | $1,810 | $945 | $4,629 | $900 | $1,300 |
| 659E31000 LIME | 0.28 ACRE | $698 | $50.39 | $3,220 | $1.00 | $100 |
| 659E35000 WATER | 7.46 MGAL | $1.00 | $1.05 | $67.07 | $1.00 | $10.00 |
| 670E00520 SLOPE EROSION PROTECTION MAT, TYPE B | 212 SY | $1.72 | $3.62 | $8.54 | $5.00 | $6.25 |
| 605E31100 AGGREGATE DRAINS | 156 FT | $11.82 | $8.20 | $21.35 | $34.62 | $15.00 |
| 611E02000 8" CONDUIT, TYPE C | 8 FT | $55.05 | $153 | $88.00 | $53.25 | $170 |
| 611E04600 12" CONDUIT, TYPE C | 16 FT | $47.32 | $116 | $51.61 | $76.10 | $120 |
| 611E98510 CATCH BASIN, NO. 2-3 | 1 EACH | $2,628 | $8,270 | $4,770 | $4,199 | $2,800 |
| 304E20000 AGGREGATE BASE (DRIVEWAYS) | 17 CY | $99.56 | $152 | $204 | $121 | $126 |
| 407E10000 TACK COAT | 70 GAL | $7.95 | $2.63 | $8.12 | $24.14 | $2.70 |
| 408E10001 PRIME COAT, AS PER PLAN | 86 GAL | $10.51 | $15.75 | $12.00 | $24.14 | $16.50 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 3 EACH | $20.00 | $20.64 | $37.26 | $1,267 | $48.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.08 MILE | $12,373 | $9,975 | $11,000 | $9,500 | $10,800 |
| 642E00300 CENTER LINE, TYPE 1 Section 5 - TRAFFIC CONTROL - Totals Awd $1,544.74 2 $1,258.92 3 $1,431.78 4 $4,940.01 5 $1,440.00 | 0.04 MILE | $12,373 | $9,975 | $11,000 | $9,500 | $10,800 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $8,104.19 2 $8,389.50 3 $7,205.00 4 $10,225.61 5 $7,144.00 | 2 SNMT | $1,114 | $945 | $990 | $1,227 | $972 |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $500 | $3,625 | $2,500 | $1,416 | $1,400 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →