STA-Sippo Valley Trail Bridge 8
STA County · est $0.8M
Bid dateThursday, April 9—
Awarded toMATT WINTERS EXCAVATION LLC$744,413
STA County · est $0.8M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 513E95020 STRUCTURAL STEEL, MISC.: PREFABRICATED BRIDGE | 1 LS | $311,945 | $312k | 42% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $111,900 | $112k | 15% |
| 507E00550 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 930 FT | $85 | $79k | 11% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $40,500 | $41k | 5% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 43 CY | $775 | $33k | 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $24,000 | $24k | 3% |
| 624E10000 MOBILIZATION Section 5 - INCIDENTALS - Totals Awd $37,400.00 2 $220,640.00 3 $83,400.00 4 $73,500.00 5 $138,000.00 | 1 LS | $20,000 | $20k | 3% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 4,900 LB | $3 | $15k | 2% |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA Section 4 - STRUCTURE OVER 20 FOOT SPAN (STA-SVT-008 - Totals Awd $659,501.00 2 $515,236.00 3 $669,343.00 4 $722,406.00 5 $1,001,020.00 | 52 CY | $205 | $11k | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,600 | $11k | 1% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 19 more items below.
| Item | Quantity | R1Matt Winters Excavation LLC | R2Stanley Miller Construction Company | R3J D Williamson Construction CO INC | R4Black Horse Bridge Construction INC | R5S E T INC | % of bid |
|---|---|---|---|---|---|---|---|
| 513E95020 STRUCTURAL STEEL, MISC.: PREFABRICATED BRIDGE | 1 LS | $311,945 | $252,540 | $225,000 | $375,000 | $540,000 | 43% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $111,900 | $10,611 | $158,000 | $65,120 | $55,000 | 15% |
| 507E00550 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 930 FT | $85.00 | $60.00 | $50.00 | $70.00 | $78.00 | 11% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $40,500 | $43,945 | $20,000 | $83,000 | $35,000 | 6% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 43 CY | $775 | $723 | $1,000 | $1,000 | $1,000 | 5% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $24,000 | $34,389 | $60,000 | $500 | $165,000 | 3% |
| 624E10000 MOBILIZATION Section 5 - INCIDENTALS - Totals Awd $37,400.00 2 $220,640.00 3 $83,400.00 4 $73,500.00 5 $138,000.00 | 1 LS | $20,000 | $183,100 | $40,000 | $30,000 | $100,000 | 3% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 4,900 LB | $3.00 | $1.90 | $2.00 | $2.50 | $2.05 | 2% |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA Section 4 - STRUCTURE OVER 20 FOOT SPAN (STA-SVT-008 - Totals Awd $659,501.00 2 $515,236.00 3 $669,343.00 4 $722,406.00 5 $1,001,020.00 | 52 CY | $205 | $234 | $140 | $220 | $255 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,600 | $9,340 | $10,000 | $9,500 | $20,000 | 1% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG Section 3 - PAVEMENT - Totals Awd $13,350.00 2 $17,530.00 3 $11,564.00 4 $12,448.00 5 $14,835.50 | 9 CY | $1,150 | $1,440 | $800 | $800 | $1,200 | 1% |
| 607E98000 FENCE, MISC.:WOOD FENCE | 117 FT | $85.00 | $86.00 | $90.00 | $120 | $76.00 | 1% |
| 503E21100 UNCLASSIFIED EXCAVATION | 240 CY | $40.00 | $97.00 | $100 | $115 | $110 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $9,000 | $16,000 | $12,000 | $24,750 | $100,000 | 1% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 55 CY | $135 | $168 | $115 | $190 | $60.00 | 1% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $9,109.00 2 $9,870.00 3 $7,426.12 4 $8,501.00 5 $8,477.00 | 6,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 507E00500 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, DRIVE | 870 FT | $6.00 | $19.00 | $45.00 | $11.00 | $24.00 | 1% |
| 523E20000 DYNAMIC LOAD TESTING | 1 EACH | $3,400 | $5,124 | $5,000 | $6,000 | $5,200 | 0% |
| 516E12201 STRUCTURAL STEEL EXPANSION JOINT, AS PER PLAN | 28 FT | $120 | $165 | $675 | $300 | $275 | 0% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $2,800 | $4,000 | $4,000 | $10,000 | $6,000 | 0% |
| Item | Quantity | R1Matt Winters Excavation LLC | R2Stanley Miller Construction Company | R3J D Williamson Construction CO INC | R4Black Horse Bridge Construction INC | R5S E T INC |
|---|---|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 117 SY | $15.00 | $8.00 | $5.00 | $7.00 | $27.00 |
| 203E10000 EXCAVATION | 29 CY | $27.00 | $67.00 | $20.00 | $48.00 | $100 |
| 203E20000 EMBANKMENT | 6 CY | $95.00 | $80.00 | $20.00 | $80.00 | $115 |
| 690E91000 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $1,500 | $2,500 | $1,500 | $3,000 | $2,200 |
| 690E98400 SPECIAL - SURVEY CONTROL VERIFICATION Section 1 - ROADWAY - Totals Awd $25,053.00 2 $33,343.00 3 $26,815.00 4 $47,481.00 5 $120,041.00 | 1 LS | $1,500 | $1,422 | $1,500 | $3,000 | $2,200 |
| 659E00300 TOPSOIL | 9 CY | $90.00 | $56.00 | $115 | $190 | $185 |
| 659E10000 SEEDING AND MULCHING | 76 SY | $30.00 | $44.00 | $5.00 | $10.00 | $10.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.02 TON | $850 | $750 | $475 | $1,000 | $1,000 |
| 659E31000 LIME | 0.02 ACRE | $50.00 | $300 | $31.00 | $500 | $600 |
| 659E35000 WATER | 1 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $20.00 |
| 204E10000 SUBGRADE COMPACTION | 124 SY | $7.00 | $2.00 | $10.00 | $11.00 | $4.00 |
| 304E20000 AGGREGATE BASE | 19 CY | $110 | $226 | $160 | $200 | $185 |
| 407E10000 TACK COAT | 7 GAL | $6.00 | $4.00 | $12.00 | $12.00 | $3.50 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 28 SY | $75.00 | $95.00 | $39.00 | $55.00 | $40.00 |
| 516E14014 INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 34 FT | $35.00 | $47.00 | $75.00 | $48.00 | $44.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 66 FT | $11.00 | $22.00 | $21.00 | $14.00 | $11.50 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 40 FT | $10.00 | $22.00 | $34.00 | $22.00 | $8.00 |
| 619E16010 FIELD OFFICE, TYPE B | 12 MNTH | $100 | $500 | $1,200 | $1,000 | $500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,800 | $18,200 | $15,000 | $12,000 | $6,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →