Figure 0.1 · BRIEFING
BID #260223 · ODOTRESULT · awarded Apr 23

SCI-Shawnee SF Bridges

SCI County · est $0.3M

Bid dateThursday, April 23
Awarded toAXIS CIVIL CONSTRUCTION LLC$267,440
read → connected → answeredcassandri

Project scope

Bid form · ODOT

17ITEMS
  • Structures / Bridge47%
  • Earthwork18%
  • Concrete Paving12%
  • Mobilization & General12%
  • Erosion & Landscaping6%
  • Maintaining Traffic6%

Top items by winning bid

ItemQtyUnit priceExtended%
511E71100 CONCRETE, MISC.: CLASS QC5, ABUTMENT Section 3 - STRUCTURE REPAIR (SCI-001SF-0275/SFN 732 - Totals Awd $125,196.00 2 $113,520.00 3 $137,383.0016 CY$3,250$52k19%
511E71100 CONCRETE, MISC.: CLASS QC5, ABUTMENT Section 4 - STRUCTURE REPAIR (SCI-006SF-1244/SFN 732 - Totals Awd $108,694.00 2 $99,505.00 3 $121,547.0013 CY$3,450$45k17%
202E11200 PORTIONS OF STRUCTURE REMOVED1 LS$18,000$18k7%
202E11200 PORTIONS OF STRUCTURE REMOVED1 LS$18,000$18k7%
503E11100 COFFERDAMS AND EXCAVATION BRACING1 LS$16,000$16k6%
503E11100 COFFERDAMS AND EXCAVATION BRACING1 LS$16,000$16k6%
503E21300 UNCLASSIFIED EXCAVATION1 LS$15,000$15k6%
614E11000 MAINTAINING TRAFFIC1 LS$15,000$15k6%
510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT339 EACH$40$14k5%
503E21300 UNCLASSIFIED EXCAVATION1 LS$11,000$11k4%

Per-bidder unit pricing

ODOT bid tab line items with each bidder’s unit price. Top 17items by winning bid’s extended amount.

Rank 1Axis Civil Construction LLC$267kRank 2R C Construction Company And Son INC$294kRank 3D G M INC$297k
ItemQuantityR1Axis Civil Construction LLCR2R C Construction Company And Son INCR3D G M INC
511E71100 CONCRETE, MISC.: CLASS QC5, ABUTMENT Section 3 - STRUCTURE REPAIR (SCI-001SF-0275/SFN 732 - Totals Awd $125,196.00 2 $113,520.00 3 $137,383.0016 CY$3,250$1,800$3,600
511E71100 CONCRETE, MISC.: CLASS QC5, ABUTMENT Section 4 - STRUCTURE REPAIR (SCI-006SF-1244/SFN 732 - Totals Awd $108,694.00 2 $99,505.00 3 $121,547.0013 CY$3,450$1,800$3,350
202E11200 PORTIONS OF STRUCTURE REMOVED1 LS$18,000$18,500$20,500
202E11200 PORTIONS OF STRUCTURE REMOVED1 LS$18,000$18,500$25,000
503E11100 COFFERDAMS AND EXCAVATION BRACING1 LS$16,000$15,000$500
503E11100 COFFERDAMS AND EXCAVATION BRACING1 LS$16,000$15,000$500
503E21300 UNCLASSIFIED EXCAVATION1 LS$15,000$12,500$30,000
614E11000 MAINTAINING TRAFFIC1 LS$15,000$28,000$5,000
510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT339 EACH$40.00$75.00$30.00
503E21300 UNCLASSIFIED EXCAVATION1 LS$11,000$12,500$30,000
509E10001 EPOXY COATED STEEL REINFORCEMENT, AS PER PLAN2,659 LB$4.00$5.00$7.00
510E10000 DOWEL HOLES WITH NONSHRINK, NONMETALLIC GROUT262 EACH$40.00$75.00$30.00
624E10000 MOBILIZATION Section 5 - INCIDENTALS - Totals Awd $28,500.00 2 $75,500.00 3 $33,500.001 LS$10,000$25,000$8,500
509E10001 EPOXY COATED STEEL REINFORCEMENT, AS PER PLAN2,091 LB$4.00$5.00$7.00
832E30000 EROSION CONTROL Section 1 - EROSION CONTROL - Totals Awd $5,000.00 2 $5,000.00 3 $5,000.005,000 EACH$1.00$1.00$1.00
103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM1 LS$3,500$22,500$20,000
616E10000 WATER Section 2 - MAINTENANCE OF TRAFFIC - Totals Awd $50.00 2 $50.00 3 $50.0050 MGAL$1.00$1.00$1.00

Project details

Description
SCI-Shawnee SF Bridges
Type of work
Bridge

How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →