ATH-SR 13-13.71
ATH County · est $1.0M
Bid dateThursday, January 15—
Awarded toD G M INC$886,436.25
ATH County · est $1.0M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 203E10000 EXCAVATION | 25,147 CY | $20 | $503k | 57% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $80,000 | $80k | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $57,500 | $58k | 6% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $45,000 | $45k | 5% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG Section 4 - PAVEMENT - Totals Awd $28,394.70 2 $33,098.25 3 $32,880.69 4 $42,870.00 5 $27,878.16 6 $25,788.00 7 $27,015.00 | 72 CY | $450 | $32k | 4% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $104,855.22 2 $140,500.00 3 $112,000.00 4 $145,000.00 5 $135,000.00 6 $137,500.00 7 $104,157.50 | 1 LS | $25,000 | $25k | 3% |
| 208E15000 PRESPLITTING | 581 SY | $40 | $23k | 3% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $45,403.91 2 $52,045.00 3 $43,078.50 4 $102,564.00 5 $102,810.67 6 $59,839.50 7 $51,847.73 | 15,000 EACH | $1 | $15k | 2% |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 7,423 SY | $2 | $15k | 2% |
| 622E41100 PORTABLE BARRIER, UNANCHORED Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $36,307.76 2 $29,410.00 3 $36,208.00 4 $41,470.00 5 $32,420.84 6 $63,244.00 7 $35,337.80 | 480 FT | $30 | $14k | 2% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 21 more items below.
| Item | Quantity | R1D G M INC | R2Allard Excavation LLC | R3Shelly & Sands INC | R4R C Construction Company And Son INC | R5Alan Stone CO INC | R6Mc Kee Paving & Sealing LLC | R7Sunesis Construction CO | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 203E10000 EXCAVATION | 25,147 CY | $20.00 | $26.00 | $24.50 | $23.00 | $30.00 | $35.00 | $63.62 | 58% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $80,000 | $65,000 | $121,300 | $125,000 | $140,000 | $90,000 | $103,400 | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $57,500 | $38,874 | $29,000 | $30,000 | $70,000 | $40,000 | $38,695 | 7% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $45,000 | $7,456 | $5,000 | $30,000 | $18,000 | $20,000 | $11,423 | 5% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG Section 4 - PAVEMENT - Totals Awd $28,394.70 2 $33,098.25 3 $32,880.69 4 $42,870.00 5 $27,878.16 6 $25,788.00 7 $27,015.00 | 72 CY | $450 | $386 | $450 | $575 | $378 | $350 | $365 | 4% |
| 624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $104,855.22 2 $140,500.00 3 $112,000.00 4 $145,000.00 5 $135,000.00 6 $137,500.00 7 $104,157.50 | 1 LS | $25,000 | $50,000 | $57,000 | $45,000 | $25,000 | $65,000 | $43,939 | 3% |
| 208E15000 PRESPLITTING | 581 SY | $40.00 | $37.00 | $19.00 | $175 | $75.00 | $45.00 | $92.60 | 3% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $45,403.91 2 $52,045.00 3 $43,078.50 4 $102,564.00 5 $102,810.67 6 $59,839.50 7 $51,847.73 | 15,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 7,423 SY | $2.00 | $2.00 | $1.00 | $5.00 | $8.87 | $2.00 | $2.22 | 2% |
| 622E41100 PORTABLE BARRIER, UNANCHORED Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $36,307.76 2 $29,410.00 3 $36,208.00 4 $41,470.00 5 $32,420.84 6 $63,244.00 7 $35,337.80 | 480 FT | $30.00 | $43.00 | $32.00 | $30.00 | $21.00 | $81.00 | $43.49 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $13,000 | $8,525 | $21,000 | $40,000 | $22,000 | $12,500 | $10,100 | 1% |
| 208E16000 HYDROLOGIST Section 1 - ROADWAY - Totals Awd $760,311.00 2 $623,180.00 3 $813,120.50 4 $855,056.00 5 $984,385.00 6 $1,025,640.00 7 $1,819,752.74 | 1 LS | $12,000 | $4,547 | $38,000 | $10,000 | $21,000 | $18,000 | $30,400 | 1% |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $10,000 | $3,524 | $9,932 | $10,000 | $8,231 | $10,500 | $9,934 | 1% |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $7,000 | $6,820 | $6,000 | $20,000 | $6,673 | $13,000 | $4,284 | 1% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 6 SNMT | $1,000 | $1,705 | $1,500 | $2,000 | $2,000 | $1,800 | $865 | 1% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,500 | $697 | $2,350 | $3,000 | $3,400 | $4,500 | $2,381 | 1% |
| 208E12000 BLASTING CONSULTANT | 1 LS | $3,000 | $7,388 | $7,000 | $10,000 | $8,500 | $6,800 | $18,500 | 0% |
| 621E00100 RPM | 18 EACH | $160 | $171 | $150 | $200 | $233 | $175 | $160 | 0% |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,500 | $2,273 | $2,000 | $10,000 | $3,000 | $3,500 | $3,100 | 0% |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 48 FT | $45.00 | $36.00 | $32.00 | $35.00 | $19.90 | $45.00 | $32.00 | 0% |
| Item | Quantity | R1D G M INC | R2Allard Excavation LLC | R3Shelly & Sands INC | R4R C Construction Company And Son INC | R5Alan Stone CO INC | R6Mc Kee Paving & Sealing LLC | R7Sunesis Construction CO |
|---|---|---|---|---|---|---|---|---|
| 208E10000 PRE-BLAST CONDITION SURVEY | 1 LS | $1,000 | $4,647 | $4,280 | $10,000 | $6,500 | $1,250 | $4,800 |
| 208E13000 AIR BLAST AND NOISE CONTROL | 1 LS | $500 | $1,705 | $7,700 | $10,000 | $5,200 | $1,650 | $3,500 |
| 208E14000 VIBRATION CONTROL AND MONITORING | 1 LS | $500 | $1,705 | $7,700 | $10,000 | $5,200 | $1,650 | $5,500 |
| 659E10000 SEEDING AND MULCHING | 538 SY | $1.00 | $2.00 | $2.00 | $5.00 | $4.27 | $2.25 | $3.38 |
| 659E20000 COMMERCIAL FERTILIZER | 1.07 TON | $1,500 | $1,421 | $1,250 | $2,900 | $979 | $1,300 | $845 |
| 659E31000 LIME | 1.64 ACRE | $300 | $171 | $150 | $2,800 | $400 | $200 | $161 |
| 659E35000 WATER | 64 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E97300 CONDUIT, MISC.: REVIEW OF DRAINAGE FACILITIES Section 3 - DRAINAGE - Totals Awd $1,564.00 2 $500.00 3 $500.00 4 $15,000.00 5 $2,300.00 6 $1,500.00 7 $5,508.56 | 1 LS | $500 | $1,564 | $500 | $15,000 | $2,300 | $1,500 | $5,509 |
| 407E10000 TACK COAT | 147 GAL | $4.75 | $4.10 | $3.27 | $10.00 | $4.72 | $4.00 | $5.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 18 EACH | $1.00 | $10.00 | $31.00 | $50.00 | $24.15 | $5.00 | $30.16 |
| 630E08600 SIGN POST REFLECTOR | 2 EACH | $140 | $114 | $100 | $250 | $60.00 | $115 | $100 |
| 630E80100 SIGN, FLAT SHEET (W1-6) (24"x48") | 16 SF | $50.00 | $91.00 | $80.00 | $250 | $34.43 | $100 | $80.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $40.00 | $28.00 | $250 | $50.00 | $31.14 | $300 | $250 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 4 EACH | $30.00 | $28.00 | $125 | $50.00 | $37.13 | $150 | $125 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.26 MILE | $3,500 | $2,273 | $2,000 | $9,500 | $6,519 | $4,000 | $3,000 |
| 642E00300 CENTER LINE, TYPE 1 Section 5 - TRAFFIC CONTROL - Totals Awd $8,020.09 2 $7,703.00 3 $8,314.00 4 $14,685.00 5 $9,634.99 6 $10,380.00 7 $8,608.88 | 0.13 MILE | $3,500 | $4,547 | $4,000 | $9,500 | $11,359 | $7,000 | $3,000 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 16 HOUR | $60.00 | $97.00 | $105 | $20.00 | $80.00 | $125 | $75.00 |
| 614E11630 INCREASED BARRIER DELINEATION | 480 FT | $2.00 | $2.00 | $1.40 | $10.00 | $3.30 | $2.25 | $1.81 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 0.12 MILE | $14,000 | $9,548 | $8,400 | $12,500 | $5,024 | $9,500 | $12,500 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 24 FT | $15.00 | $14.00 | $12.00 | $100 | $1.00 | $12.25 | $10.00 |
| 616E10000 WATER | 50 MGAL | $1.00 | $1.00 | $70.00 | $1.00 | $1.00 | $1.00 | $14.04 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →