Figure 0.1 · BRIEFING
BID #260302 · ODOTPRE‑BID · 12 DAYS

Minor Reconstruction

Mercer County

Bid dateThursday, June 11
read → connected → answeredcassandri

Project scope

Bid form · ODOT

24ITEMS
  • PAVEMENT29%
  • INCIDENTALS21%
  • EROSION CONTROL17%
  • TRAFFIC CONTROL17%
  • ROADWAY13%
  • DRAINAGE4%

Cost concentration table renders only when the active letting’s own line items are present. The donut above is aggregated from this bid.

Bid item schedule

As advertised by ODOT24 pay items with quantities and units. Contractor unit prices appear here once bids open.

#ItemDescriptionQuantity
1202E23000PAVEMENT REMOVED1,103 SY
2203E10000EXCAVATION292 CY
3204E60000SPECIAL - GEOCELL, SUBGRADE, 6" THICKNESS1,357 SY
4659E10000SEEDING AND MULCHING360 SY
5659E20000COMMERCIAL FERTILIZER0.04 TON
6659E35000WATER3 MGAL
7832E30000EROSION CONTROL6,000 EACH
8605E31100AGGREGATE DRAINS102 FT
9301E56000ASPHALT CONCRETE BASE, PG64-22, (449)215 CY
10304E20000AGGREGATE BASE298 CY
11407E20000NON-TRACKING TACK COAT180 GAL
12411E10000STABILIZED CRUSHED AGGREGATE303 CY
13441E70100ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG70-22M49 CY
14441E70300ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2, (449)52 CY
15617E10100COMPACTED AGGREGATE18 CY
16621E00100RPM6 EACH
17621E54000RAISED PAVEMENT MARKER REMOVED6 EACH
18642E00104EDGE LINE, 6", TYPE 10.14 MILE
19642E00300CENTER LINE, TYPE 10.07 MILE
20103E05000PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYMENT BONDLump sum
21614E11000MAINTAINING TRAFFICLump sum
22614E12420DETOUR SIGNINGLump sum
23623E10000CONSTRUCTION LAYOUT STAKES AND SURVEYINGLump sum
24624E10000MOBILIZATION PID #: 125150 Contract ID: MER125150 EDGE Goal: 5.0% MERCER MER/LOG-SR 49/SR 559-23.45/03.53 NON-FEDERAL MINOR RECONSTRUCTION THE 2023 CONSTRUCTION AND MATERIAL SPECIFICATION BOOK IS PART OF THE BIDDING DOCUMENTS ON THIS PROJECT PROPOSAL STATE OF OHIO DEPARTMENT OF TRANSPORTATION Pamela Boratyn, Director June 11, 2026 Submitted by Bidder IdLump sum

Project details

Description
MINOR RECONSTRUCTION
Type of work
Minor reconstruction

How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →